Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
3 results found in 4 ms Page 1 of 1
Building and Implementing the Phoenix Pay System
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Office of theAuditor Generalof Canada , issued in 2018
Risk cases: 3
The Annual Municipal Accounts as a basis for comparing municipalities - are the cost indicator reliable?
Municipal accounting: more standardized or more controlled Municipalities report among others, their costs, which cannot be directly attributed to any specific activity, product, or service. Standardized taxonomies exist, but they are not applied uniformly. Swedish NAO traces ramifications: lower ability to compare municipalities' data and need of more central level control.
Full description
Swedish National Audit Office , issued in 2018
Risk cases: 3
Improving government’s planning and spending framework
Value for money vs. short-term planning NAO reviewed the UK government's progress in improving their planning and spending framework. The auditors found that the complex structure and lack of longer term perspective in planning form a significant obstacle to fully benefit from the framework.
Full description
National Audit Office , issued in 2018
Risk cases: 7
3 results found. Page 1 of 1