Insufficient monitoring of consultancy work in large-scale IT projects
Insufficient monitoring of consultancy work in large-scale IT projects The German Federal Ministry of the Interior did not sufficiently plan, monitor and control consultancy work in two large-scale IT projects, not being thus able to evaluate the amount of work done and pay accordingly. It was recommended by SAI the establishment of a quality management system and its application mandatory for large-scale IT projects
Full description
Insufficient monitoring of consultancy work in large-scale IT projects The German Federal Ministry of the Interior did not sufficiently plan, monitor and control consultancy work in two large-scale IT projects, not being thus able to evaluate the amount of work done and pay accordingly. It was recommended by SAI the establishment of a quality management system and its application mandatory for large-scale IT projects
Full description
Bundesrechnungshof
, issued in 2017
Risk cases: 1
Operation of the Record Systems Applied in the Eligibility Scheme of Benefits and Services Provided from the Social Security Funds
Hungarian SAI evaluated the set-up and operation of the basic registries of managing bodies (National Health Insurance Fund, Central Administration of National Pension Insurance, National Tax ... and Customs Administration), as well as the dataflow amongst them. In addition, the control system of fulfilling the data provision obligation was evaluated, as well as the IT support activities and whether ... the records had proven reliable in supporting services in compliance with eligibilities and in filtering unjustified services. The audited period covered the years 2007-2010. ... ... Well considered regulations are essential for good quality data ... State Audit Office of Hungary.has proved that date safety may depend on quality of regulations. The report on record systems of social security services casted light on risk connected with huge data ... bases managed by different entities, in a changing legal environment.
Full description
Hungarian SAI evaluated the set-up and operation of the basic registries of managing bodies (National Health Insurance Fund, Central Administration of National Pension Insurance, National Tax ... and Customs Administration), as well as the dataflow amongst them. In addition, the control system of fulfilling the data provision obligation was evaluated, as well as the IT support activities and whether ... the records had proven reliable in supporting services in compliance with eligibilities and in filtering unjustified services. The audited period covered the years 2007-2010. ... ... Well considered regulations are essential for good quality data ... State Audit Office of Hungary.has proved that date safety may depend on quality of regulations. The report on record systems of social security services casted light on risk connected with huge data ... bases managed by different entities, in a changing legal environment.
Full description
State Audit Office of Hungary
, issued in 2012
Risk cases: 2
Activities of the state in implementing the e-health system - Do the state, doctors and patients benefit from ehealth?
Estonia’s population is aging and the share of elderly people is increasing, as fewer children are being born and people are living longer. This creates a constantly growing need for health ... and social services and patients are also becoming more and more demanding about the volume and quality of the services provided. The more extensive and systematic implementation of e-health solutions helps ... make the health system more efficient, improves people’s health via more effective prevention, raises the awareness of patients and also contributes to the more reasonable use of health resources ... ... Why state, doctors and patients do not benefit from e-Health as much as they could? ... The report reviews whether the objectives set to the e-Health – ambitious multiyear program of Estonian Government - have been achieved. They are: higher quality of the health service and more ... efficient organisation of health care. As SAI Estonia found out, wide range problems started from two basic points: lack of strategic manager and unrealisitc schedule.
Full description
Estonia’s population is aging and the share of elderly people is increasing, as fewer children are being born and people are living longer. This creates a constantly growing need for health ... and social services and patients are also becoming more and more demanding about the volume and quality of the services provided. The more extensive and systematic implementation of e-health solutions helps ... make the health system more efficient, improves people’s health via more effective prevention, raises the awareness of patients and also contributes to the more reasonable use of health resources ... ... Why state, doctors and patients do not benefit from e-Health as much as they could? ... The report reviews whether the objectives set to the e-Health – ambitious multiyear program of Estonian Government - have been achieved. They are: higher quality of the health service and more ... efficient organisation of health care. As SAI Estonia found out, wide range problems started from two basic points: lack of strategic manager and unrealisitc schedule.
Full description
National Audit Office of Estonia
, issued in 2014
Risk cases: 3
Coordinated Audit on Information Technology Governance
IT governance needs awareness and SAIs' support The OLACEFS auditors found that the greatest challenge for the SAIs is to raise the awareness of the audit institutions about the importance of IT governance and the benefits that could be obtained by improving its degree of maturity. The audit was conducted by 11 SAIs and coordinated by TCU of Brasil. They concluded: 'It is important, even urgent, to invest resources to implement or enhance: the IT committees; the IT planning process; strategic IT planning; monitoring the IT contracting process; the business continuity plan; the designation of a responsible person or unit to manage security information; a risk management process; an asset inventory process; an information security committee; and a policy for access control.'
Full description
IT governance needs awareness and SAIs' support The OLACEFS auditors found that the greatest challenge for the SAIs is to raise the awareness of the audit institutions about the importance of IT governance and the benefits that could be obtained by improving its degree of maturity. The audit was conducted by 11 SAIs and coordinated by TCU of Brasil. They concluded: 'It is important, even urgent, to invest resources to implement or enhance: the IT committees; the IT planning process; strategic IT planning; monitoring the IT contracting process; the business continuity plan; the designation of a responsible person or unit to manage security information; a risk management process; an asset inventory process; an information security committee; and a policy for access control.'
Full description
Risk cases: 5
Actions of national and municipal authorities to ensure the fulfillment of the obligations under the Loan Agreement “Safety Net and Social Sector Reform Program” between the Republic of Latvia and the World Bank
The audit was planned and conducted so as to provide reasonable assurance that the national and municipal authorities have implemented the measures specified in the Program Document and ensured ... the fulfilment of the prescribed performance targets. ... ... Well coordinated information structure is necessary for the unemployment benefits system ... SAI Latvia reviewed the unemployment benefits system and analyzed the cosequences of poor information flow among state and municipalities registers. Findings presented in the report are result ... of effective use of CAAT software.
Full description
The audit was planned and conducted so as to provide reasonable assurance that the national and municipal authorities have implemented the measures specified in the Program Document and ensured ... the fulfilment of the prescribed performance targets. ... ... Well coordinated information structure is necessary for the unemployment benefits system ... SAI Latvia reviewed the unemployment benefits system and analyzed the cosequences of poor information flow among state and municipalities registers. Findings presented in the report are result ... of effective use of CAAT software.
Full description
State Audit Office of Latvia
, issued in 2011
Risk cases: 1
Incorrect payments in social insurance - Control activities of the Swedish Social Insurance Agency
the social insurance system as a whole. According to the estimates made, about SEK 1.2 billion had been underpaid and the rest was made up of benefits where the person insured had received overpayment.<br ... /> The Swedish NAO audited the work of the Government and the Swedish Social Insurance Agency to prevent incorrect payments in the period 2012–2015. The audit focused on the benefits for which the Swedish Social ... Insurance Agency is responsible. The audited benefits account for half of the insurance expenditure, half of the payments that are incorrect and for more than 70 per cent of the amount the Swedish Social ... Balance of priorities needed to reduce incorrect payments ... Role of social insurance in public finance is so substantial that reduction of incorrect payments' volume is matter of huge savings. The Swedish NAO noted positive initiatives by the Social Insurance ... Agency in this regard. However they found also, that serious problems can stem from giving higher priority to the speed of payment and customers satisfaction. They both are undoubtedly important features ... of each system, still, the prevention of incorrect payments needs strategic support to be really effective.
Full description
the social insurance system as a whole. According to the estimates made, about SEK 1.2 billion had been underpaid and the rest was made up of benefits where the person insured had received overpayment.<br ... /> The Swedish NAO audited the work of the Government and the Swedish Social Insurance Agency to prevent incorrect payments in the period 2012–2015. The audit focused on the benefits for which the Swedish Social ... Insurance Agency is responsible. The audited benefits account for half of the insurance expenditure, half of the payments that are incorrect and for more than 70 per cent of the amount the Swedish Social ... Balance of priorities needed to reduce incorrect payments ... Role of social insurance in public finance is so substantial that reduction of incorrect payments' volume is matter of huge savings. The Swedish NAO noted positive initiatives by the Social Insurance ... Agency in this regard. However they found also, that serious problems can stem from giving higher priority to the speed of payment and customers satisfaction. They both are undoubtedly important features ... of each system, still, the prevention of incorrect payments needs strategic support to be really effective.
Full description
Swedish National Audit Office
, issued in 2016
Risk cases: 3
Improving government’s planning and spending framework
Value for money vs. short-term planning NAO reviewed the UK government's progress in improving their planning and spending framework. The auditors found that the complex structure and lack of longer term perspective in planning form a significant obstacle to fully benefit from the framework.
Full description
Value for money vs. short-term planning NAO reviewed the UK government's progress in improving their planning and spending framework. The auditors found that the complex structure and lack of longer term perspective in planning form a significant obstacle to fully benefit from the framework.
Full description
National Audit Office
, issued in 2018
Risk cases: 7
The BBC’s understanding of its audiences and users
Understand your audience, BBC Audience data and insights are critical to the success of broadcasters - which is also true in the case of the world renowned British Broadcasting Corporation. Auditors reviewed the BBC's main projects and the analyst team dedicated to collect and interpret the audience related information. Data coherence, review of performance and benefits traicing - belong to key areas in need of substantial refinements.
Full description
Understand your audience, BBC Audience data and insights are critical to the success of broadcasters - which is also true in the case of the world renowned British Broadcasting Corporation. Auditors reviewed the BBC's main projects and the analyst team dedicated to collect and interpret the audience related information. Data coherence, review of performance and benefits traicing - belong to key areas in need of substantial refinements.
Full description
National Audit Office
, issued in 2019
Risk cases: 6
The National Offender Management Information System (NOMIS)
for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits. ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered
Full description
for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits. ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered
Full description
National Audit Office
, issued in 2009
Risk cases: 4
Federal Human Resources Data
Internal control weaknesses may put mission at risk GAO audited the Enterprise Human Resources Integration payroll data warehose. The American auditors pointed at problems that may impede 'leverage of these data to meet its mission and allow others to make full use' of them. The critical internal contols areas to be improved in this cas are: completeness, accuracy, and validity of information, authorization, documentation, monitoring, results' evaluation.
Full description
Internal control weaknesses may put mission at risk GAO audited the Enterprise Human Resources Integration payroll data warehose. The American auditors pointed at problems that may impede 'leverage of these data to meet its mission and allow others to make full use' of them. The critical internal contols areas to be improved in this cas are: completeness, accuracy, and validity of information, authorization, documentation, monitoring, results' evaluation.
Full description
General Accountability Office
, issued in 2016
Risk cases: 2