State funds spent on development, operation and using of data centres services
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
Supreme Audit Office of Czech Republic , issued in 2015
Risk cases: 7
Central government staff costs
Results of staff reductions The British NAO found that departments had significantly reduced numbers of their civil servants and of course salary costs at the same time. But they reduced staff numbers mainly by minimising recruitment, and the age profile of the civil service has changed. NAO pays a lot attention to what effect this has had on the future pipeline of talent and skills. It reminds also that the departments need long-term operating models to work efficiently with the staff reduced.
Full description
National Audit Office , issued in 2015
Risk cases: 5
Cost-intensive data centres stood idle for years
Idle data centres As found by the German SAI, some of costly Federal data centres stood largely idle. The Ministry failed to adequately assess the project risks. The Ministry needs to avoid similar shortcomings in the proposed federal IT consolidation project.
Full description
Bundesrechnungshof , issued in 2016
Risk cases: 1
Public access point to the Polish e-Administration
and public report issued in March 2009. Primary goal of th presentation was intended to illustrate the use of 'e-Government Algorithm' elaborated by EUROSAI IT Working Group in 2005. One of issues mede better ... Coordinated audit series (46 auditees) focused on a web solution applied to give an easy access to Government e-services (the project planned to be completed in 2013) The audit was performed in 2008 ... known by the audit was 'Project Frameworks vs Public Procurement'. ... ... Buyer, provider and methodologies need a balance ... old EUROSAI IT Wg 'Algorithm approach' and focuses on procurement systemic problems. ... Presentation based on a vast audit by Polish SAI which subject was of big network project aiming to provide one access point to Government and Selfgovernments services. The presentation illustrates
Full description
Supreme Audit Office of Poland , issued in 2008
Risk cases: 3
The Board of Audit and Inspection (BAI) conducted an audit on the information systems in the area of service delivery to improve the system’s efficiency and convenience.
Korea was recognized as an Information Technology (IT) powerhouse by the international community of the UN in 2010. Such an achievement is attributable to the significant investments that the Korean ... government has commissioned toward improving the country’s information infrastructure within a short period of time.<br/> The government is investing 1 trillion won every year in an e-government project ... for citizens in the welfare and employment sectors by utilizing the renewed information infrastructure.<br/> However, the information system of some government ministries proved to have overlapping functions ... Enormous IT investments require tremendous coordination ... Korean government is investing 1 trillion won in e-government projectsevery year. Thus, the country has earned a reputation for the IT powerhouse. Apart from undeniable advantages, the huge scale ... and the speed, the information technologies are implemented with, cause some problems to be tackled. The SAI Korea turns special atention to two of them: overlapping functionalities and interconnectivity issues.
Full description
Board of Audit and Inspection of Korea , issued in 2011
Risk cases: 3
The protection of research data at the Danish universities
The protection of research data at the Danish universities It is Rigsrevisionen’s assessment that the five largest universities are not adequately protecting their research data against unknown IT equipment. As a result, foreign actors may relatively easy gain unauthorized access to the universities’ research data.This is not considered satisfactory by Rigsrevisionen. The study shows that the five largest universities have defined guidelines for researchers’ use of software and hardware centrally, but that they have failed to centralise efforts to maintain a satisfactory level of security for research data. This is due mainly to the fact that, at some universities, researchers are allowed to bring their own devices,and at all the universities, researchers are allowed to have local administrator privileges, which gives them access to install software. Additionally, all five universities know of incidents where unknown hardware has been connected to their network.
Full description
National Audit Office of Denmark , issued in 2018
Risk cases: 3
Evaluation of the effectiveness of implementation and compliance with regulatory enactments and the legal framework of the project “E-government Portfolio”
The objective of the audit is to evaluate the effectiveness of implementation and compliance with regulatory enactments and the legal framework of the project “Egovernment Portfolio” of the national ... programme of the European Regional Development Fund (hereinafter: ERDF) of the European Union (hereinafter: EU), “Development and improvement of the infrastructural foundation for electronic governance”. ... ... Funds to absorb but no efficient project methodology? Be prepared for troubles ... Wide list of problems that can be met when more care is received by 'absorb funds' objective than by clear vision what and how can be improved. SAI Latvia's analysis shows how dangerous it can ... be for both effectiveness and financial management.
Full description
State Audit Office of Latvia , issued in 2010
Risk cases: 3
Results of the development of the state’s information systems
The National Audit Office has repeatedly audited the management and development of the state’s information technology (IT) area in the last ten years. The last audit was performed in 2005. After that ... , several measures have been implemented in the state to organise the development better and to guarantee that the systems are compatible. This audit gives an opinion of the results of development project ... management and the state’s coordination mechanism in this process. ... ... Success and failure depend on preparation ... Conclusions of performance IT audit based on a sample of government projects: business portal, land register, e-police, fire safety monitoring system, childcare information system and the document ... management system of the Defence Forces. Key problems and discussion with auditees are presented.
Full description
National Audit Office of Estonia , issued in 2010
Risk cases: 3
Building and Implementing the Phoenix Pay System
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Office of theAuditor Generalof Canada , issued in 2018
Risk cases: 3
Report on the government’s processing of confidential data on persons and companies
Rigsrevisionen has examined how eight government institutions process confidential data on persons and companies in 11 selected IT systems. The report is based on IT audits carried out in connection ... with the annual audit in the spring 2014. The purpose of the audit was to assess whether confidential data on persons and companies are adequately protected by the government institutions. ... ... Inadequate protection of confidential data ... If a government institution does not protect confidential data to the extent necessary, the risk that third parties get unauthorized access to the data is very high. In opinion of the Danish SAI ... , inadequate protection of confidential data may also erode the citizens’ and companies’ confidence in government data security. That may eventually become a barrier for the continued efforts to implement ... e-government and make government administration more efficient.
Full description
National Audit Office of Denmark , issued in 2014
Risk cases: 2