Central government staff costs
Results of staff reductions The British NAO found that departments had significantly reduced numbers of their civil servants and of course salary costs at the same time. But they reduced staff numbers mainly by minimising recruitment, and the age profile of the civil service has changed. NAO pays a lot attention to what effect this has had on the future pipeline of talent and skills. It reminds also that the departments need long-term operating models to work efficiently with the staff reduced.
Full description
Results of staff reductions The British NAO found that departments had significantly reduced numbers of their civil servants and of course salary costs at the same time. But they reduced staff numbers mainly by minimising recruitment, and the age profile of the civil service has changed. NAO pays a lot attention to what effect this has had on the future pipeline of talent and skills. It reminds also that the departments need long-term operating models to work efficiently with the staff reduced.
Full description
National Audit Office
, issued in 2015
Risk cases: 5
WannaCry Cyber Attack and the NHS
Why the British NHS became a victim of WannaCry The NAO's investigation points at the problem of insufficient powers of the cybersecurity coordinator across the health organisation. As a result no remedial actions were taken, and the cyber attack succeeded thanks to neglected precautions.
Full description
Why the British NHS became a victim of WannaCry The NAO's investigation points at the problem of insufficient powers of the cybersecurity coordinator across the health organisation. As a result no remedial actions were taken, and the cyber attack succeeded thanks to neglected precautions.
Full description
National Audit Office
, issued in 2017
Risk cases: 3
IT strategy of Swiss Federal Institute of Technology
The SFAO conducted an IT audit in 2009, in order to evaluate goal achievement and cost effectiveness of information and communication technology by Swiss Federal Institute of Technology (ETH Zurich ... ). [p. 11] ... Performance audit of IT strategy in research area ... Interesting problems of IT strategy implementation - including that of organizational authonomy skope.
Full description
The SFAO conducted an IT audit in 2009, in order to evaluate goal achievement and cost effectiveness of information and communication technology by Swiss Federal Institute of Technology (ETH Zurich ... ). [p. 11] ... Performance audit of IT strategy in research area ... Interesting problems of IT strategy implementation - including that of organizational authonomy skope.
Full description
Swiss Federal Audit Office
, issued in 2010
Risk cases: 1
Information Technology Cost Estimation Agencies Need to Address Significant Weakness in Policies and Practices
To estimate reliable cost for the sucess of an IT program by providing the basis for the informed decision making and realistic budget information. To assess the extent to which selected departments ... and agencies have appropriately implement costestimating policies an procedures(four caracteristics of a reliable cost estimation: comprehensive, well-documented, accurate, credible). ... IT cost estimation ... Check out what may go wrong with the information technology cost estimation. Results of the US GAO audit can help to identify high risk areas: comprehensiveness of estimations, their documentation ... , lack of adequacy and inadequate implementation.
Full description
To estimate reliable cost for the sucess of an IT program by providing the basis for the informed decision making and realistic budget information. To assess the extent to which selected departments ... and agencies have appropriately implement costestimating policies an procedures(four caracteristics of a reliable cost estimation: comprehensive, well-documented, accurate, credible). ... IT cost estimation ... Check out what may go wrong with the information technology cost estimation. Results of the US GAO audit can help to identify high risk areas: comprehensiveness of estimations, their documentation ... , lack of adequacy and inadequate implementation.
Full description
General Accountability Office
, issued in 2012
Risk cases: 4
Lessons learned from government ICT-projects
This audit has been performed on request of the Dutch parliament. Some newspapers mentioned government losses of four to five billion euro's on a yearly bases. These news items caused the parliament ... to request this audit. The audit has been performed in only 5 months time and consisted of the re-use of earlier performed audits. We have 'recycled' earlier findings about ICT-projects. ... 'Expensive' does not always mean 'High Quality', so... do not feed the spiral ... Excellent analysis of systemic errors commited when designing Government IT projects. The report aims at the essence of problems which are encountered far from information technologies - in: politics ... , business, psychology... Do not be mislead by date of report, it is evergreen for all who really want to know why IT projects fail.
Full description
This audit has been performed on request of the Dutch parliament. Some newspapers mentioned government losses of four to five billion euro's on a yearly bases. These news items caused the parliament ... to request this audit. The audit has been performed in only 5 months time and consisted of the re-use of earlier performed audits. We have 'recycled' earlier findings about ICT-projects. ... 'Expensive' does not always mean 'High Quality', so... do not feed the spiral ... Excellent analysis of systemic errors commited when designing Government IT projects. The report aims at the essence of problems which are encountered far from information technologies - in: politics ... , business, psychology... Do not be mislead by date of report, it is evergreen for all who really want to know why IT projects fail.
Full description
Netherlands Court of Audits
, issued in 2007
Risk cases: 3
Insufficient monitoring of consultancy work in large-scale IT projects
Insufficient monitoring of consultancy work in large-scale IT projects The German Federal Ministry of the Interior did not sufficiently plan, monitor and control consultancy work in two large-scale IT projects, not being thus able to evaluate the amount of work done and pay accordingly. It was recommended by SAI the establishment of a quality management system and its application mandatory for large-scale IT projects
Full description
Insufficient monitoring of consultancy work in large-scale IT projects The German Federal Ministry of the Interior did not sufficiently plan, monitor and control consultancy work in two large-scale IT projects, not being thus able to evaluate the amount of work done and pay accordingly. It was recommended by SAI the establishment of a quality management system and its application mandatory for large-scale IT projects
Full description
Bundesrechnungshof
, issued in 2017
Risk cases: 1
Cost-intensive data centres stood idle for years
Idle data centres As found by the German SAI, some of costly Federal data centres stood largely idle. The Ministry failed to adequately assess the project risks. The Ministry needs to avoid similar shortcomings in the proposed federal IT consolidation project.
Full description
Idle data centres As found by the German SAI, some of costly Federal data centres stood largely idle. The Ministry failed to adequately assess the project risks. The Ministry needs to avoid similar shortcomings in the proposed federal IT consolidation project.
Full description
Bundesrechnungshof
, issued in 2016
Risk cases: 1
Digitisation of municipal services
The purpose of digitisation is to increase the quality and efficiency of public services. It is a goal to make online services the norm for public administration's communication with citizens ... and the private sector. The municipal sector is a significant provider of public services, and digitisation of municipal services is therefore essential for achieving this goal.<br/>The audit surveyed the status ... , assessed the significance of and possible obstacles to digitisation of municipal services. The audit examined how the Ministry of Local Government and Modernisation's use of policy instruments contributes ... ... Municipalities have not digitised their services to any extent ... Digitisation increases the quality and efficiency of public services and municipal sector is a significant provider of public services. Report of Riksrevisjonen of Norway shows however ... , that municipalities need a substantial support to execute this demanding task. To provide them with help, the central government has to coordinate own efforts first.
Full description
The purpose of digitisation is to increase the quality and efficiency of public services. It is a goal to make online services the norm for public administration's communication with citizens ... and the private sector. The municipal sector is a significant provider of public services, and digitisation of municipal services is therefore essential for achieving this goal.<br/>The audit surveyed the status ... , assessed the significance of and possible obstacles to digitisation of municipal services. The audit examined how the Ministry of Local Government and Modernisation's use of policy instruments contributes ... ... Municipalities have not digitised their services to any extent ... Digitisation increases the quality and efficiency of public services and municipal sector is a significant provider of public services. Report of Riksrevisjonen of Norway shows however ... , that municipalities need a substantial support to execute this demanding task. To provide them with help, the central government has to coordinate own efforts first.
Full description
Office of the Auditor General of Norway
, issued in 2016
Risk cases: 2
The Ministry of the Environment lacks a compact information system and still uses 125 separate information systems and databases
The objective of the audit was to scrutinise the management of funds earmarked for the purchase and administration of ICT within the MoE and selected organisations which come under the management ... of the MoE. The audit identified the following risks: (1) non-existence of the Integrated environmental information system (IEIS) as an independent information system; (2) purchase of ICT, within the budget ... chapter of the MoE, through a state co-funded organisation CENIA which comes under the management of the MoE; (3) utilisation of the information systems. The audited period was 2010 to 2013; where relevant ... ... Ministry of the Environment manages 125 information systems and databases ... The Ministry of the Environment (MoE) has for more than 20 years a legal obligation to administer and manage an Integrated Environmental Information System (IEIS). In spite of this fact, the existing ... systems (more than 125 information systems and databases) are designed, implemented and managed as individual information systems without a direct integration into a joint point of reference.
Full description
The objective of the audit was to scrutinise the management of funds earmarked for the purchase and administration of ICT within the MoE and selected organisations which come under the management ... of the MoE. The audit identified the following risks: (1) non-existence of the Integrated environmental information system (IEIS) as an independent information system; (2) purchase of ICT, within the budget ... chapter of the MoE, through a state co-funded organisation CENIA which comes under the management of the MoE; (3) utilisation of the information systems. The audited period was 2010 to 2013; where relevant ... ... Ministry of the Environment manages 125 information systems and databases ... The Ministry of the Environment (MoE) has for more than 20 years a legal obligation to administer and manage an Integrated Environmental Information System (IEIS). In spite of this fact, the existing ... systems (more than 125 information systems and databases) are designed, implemented and managed as individual information systems without a direct integration into a joint point of reference.
Full description
Supreme Audit Office of Czech Republic
, issued in 2015
Risk cases: 7
Finally updating the central information system for VAT control
IT system to support combating VAT frauds German Bundesrechnungshof demanded to update the IT system, which plays crucial role in the European system of fighting fraud related to the Value Added Tax (VAT). This BRH's case shows that reminding about appropriate follow-up can be as important as the very recommendation.
Full description
IT system to support combating VAT frauds German Bundesrechnungshof demanded to update the IT system, which plays crucial role in the European system of fighting fraud related to the Value Added Tax (VAT). This BRH's case shows that reminding about appropriate follow-up can be as important as the very recommendation.
Full description
Bundesrechnungshof
, issued in 2014
Risk cases: 1