State funds spent on development, operation and using of data centres services
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
Supreme Audit Office of Czech Republic , issued in 2015
Risk cases: 7
Information security work at nine agencies
Difficulties in achieving appropriate IT security Together with the Swedish NAO we assume that the picture that emerges at the agencies audited applies also to most of the other agencies in the public administration. The information security work is not given high enough priority in relation to the risks that exist. This applies to both the Government, which should have been clearer in its directions to agencies on this matter, and to agency managements, which did not give priority to the work of information security to the extent required. Much indicates that it is difficult for many agencies to achieve an appropriate level of information security work.
Full description
Swedish National Audit Office , issued in 2016
Risk cases: 4
Population registration - uphill quality work
Quality of population register The Swedish NAO notes that quality requirements for population registration are highand that quality work should concentrate on the errors that have the most seriousconsequences for society. They point then at the need to increase knowledge of the errors, improve IT tools and governance to receive more quality work.
Full description
Swedish National Audit Office , issued in 2017
Risk cases: 4
Insufficient monitoring of consultancy work in large-scale IT projects
Insufficient monitoring of consultancy work in large-scale IT projects The German Federal Ministry of the Interior did not sufficiently plan, monitor and control consultancy work in two large-scale IT projects, not being thus able to evaluate the amount of work done and pay accordingly. It was recommended by SAI the establishment of a quality management system and its application mandatory for large-scale IT projects
Full description
Bundesrechnungshof , issued in 2017
Risk cases: 1
VA ACQUISITION MANAGEMENT: Supply Chain Management and COVID-19 Response
Pandemic points up weaknesses of procurement solutions US Department of Veterans Affairs acquires hundreds of millions of dollars-worth of medical supplies each year. The Medical-Surgical Prime Vendor-Next Generation (MSPV-NG) is one of its key initiatives to modrnize its processes. GAO auditor pointed in their previous audits that the approach lacked an effective medical supply procurement strategy, clinician involvement, and reliable data systems. In time of the pandemic, the problem seems even more difficult to deal with.
Full description
US Government Accountability Office , issued in 2019
Risk cases: 4
Products sold on the European market: unravelling the system of CE marking
Problems with general picture The Netherlands National Court of Audit was interested in finding out whether anyone keeps track of all the actors involved in the process of system of European Union product markings. The interest was aroused by an observation that the vast majority of the questions raised about the system were prompted by incidents and that the questioners did not generally appear to be interested in the operation of the system as a whole...
Full description
The Netherlands Court of Audit , issued in 2017
Risk cases: 5
Audit of the Government, Government-guaranteed and Municipal Debt Management Information Systems in the Ministry of Finance of the Republic of Bulgaria
The main audit question studied during the audit was: Are the government, government-guaranteed (SDMS) and municipal debt management information systems (CMDR) at the Ministry of Finance effective ... ? The audit covered the period from 01.01.2013 to 31.12.2013 and investigated four major areas: IT system strategy and general management; IT security and controls against disasters; Operational controls ... and Documentation; Application Controls. ... ... Even effective and modern IT systems require improvements and updates to ensure their security and accountability ... For the management of the government, government-guaranteed and municipal debt the Ministry of Finance has established an advanced integrated information infrastructure. According to Bulgarian SAI ... the established system is effective and provides updated, complete and correct information. Nevertheless the audit report points out areas of security, application controls as well as documentation as the subjects ... that need further improvement and optimization.
Full description
Bulgarian National Audit Office , issued in 2014
Risk cases: 3
Use of consultants and temporary staff
New skills needed in a longer term UK NAO: Used well, consultants and temporary staff can be an important source of specialist skills and capabilities that are uneconomic for departments to maintain in their permanent staff. Since 2009-10, the government has used spending controls to reduce its use of consultants and temporary staff, and by 2014-15 spending had fallen by £1.5 billion. However, spending has increased by between £400 million and £600 million since 2011-12, suggesting that this was more of a short-term reduction than a sustainable strategy. In the longer term, departments will need to develop workforce, skills and capacity plans to reduce their dependence on external skills. They will need to improve their strategic workforce planning to determine where they can deploy existing staff, where they need to recruit, and where they need to engage temporary resources. Without this, departments cannot demonstrate that they are achieving value for money from the use of consultants and temporary staff.
Full description
National Audit Office , issued in 2016
Risk cases: 7
Management of Information Resources of the Ministry of Agriculture
The Ministry of Agriculture of the Republic of Lithuania has managed 32 information systems and registers. Of these, 24 ones are managed, developed and upgraded by a state enterprise subordinate ... to the Ministry of Agriculture, the Agricultural Information and Rural Business Centre. The annual amount allocated by the Ministry for the maintenance of the Centre totals LTL 17.5 million on average ... . The objective of the audit was to assess the general and development controls of the information resources of the Ministry of Agriculture. The audit was conducted at the Ministry of Agriculture and the state ... ... Without appropiate IT management  it is hard to achieve reliable, consistent and secure systems for agriculture ... Since 1996 the Ministry has been using information systems of varying complexity for collecting and processing data, including personal data. The Ministry of Agriculture of the Republic of Lithuania ... has managed 32 information systems and registers. SAI of Lithuania revealed that systems were not well mantained what affected use of funds devoted to the systemsand also their legality and security.
Full description
National Audit Office of the Republic of Lithuania , issued in 2013
Risk cases: 2
Municipalities’ internal control system – Audit of the establishment and operation of the internal control system of municipalities – on the audit of Rudabánya
Incomplete internal control The SAI Hungary published the compliance audit of the establishment and operation of the internal control system, as well as certain investment decisions, their implementation and accounting at the Local Government of Rudabánya. Apart from positive findings, some accounting irregularities and insufficient controls established to ensure organisational integrity were pointed out.
Full description
State Audit Office of Hungary , issued in 2018
Risk cases: 2
previous 109 results found. Page 10 of 11 next