Audit of the Government, Government-guaranteed and Municipal Debt Management Information Systems in the Ministry of Finance of the Republic of Bulgaria
The main audit question studied during the audit was: Are the government, government-guaranteed (SDMS) and municipal debt management information systems (CMDR) at the Ministry of Finance effective ... ? The audit covered the period from 01.01.2013 to 31.12.2013 and investigated four major areas: IT system strategy and general management; IT security and controls against disasters; Operational controls ... and Documentation; Application Controls. ... ... Even effective and modern IT systems require improvements and updates to ensure their security and accountability ... For the management of the government, government-guaranteed and municipal debt the Ministry of Finance has established an advanced integrated information infrastructure. According to Bulgarian SAI ... the established system is effective and provides updated, complete and correct information. Nevertheless the audit report points out areas of security, application controls as well as documentation as the subjects ... that need further improvement and optimization.
Full description
The main audit question studied during the audit was: Are the government, government-guaranteed (SDMS) and municipal debt management information systems (CMDR) at the Ministry of Finance effective ... ? The audit covered the period from 01.01.2013 to 31.12.2013 and investigated four major areas: IT system strategy and general management; IT security and controls against disasters; Operational controls ... and Documentation; Application Controls. ... ... Even effective and modern IT systems require improvements and updates to ensure their security and accountability ... For the management of the government, government-guaranteed and municipal debt the Ministry of Finance has established an advanced integrated information infrastructure. According to Bulgarian SAI ... the established system is effective and provides updated, complete and correct information. Nevertheless the audit report points out areas of security, application controls as well as documentation as the subjects ... that need further improvement and optimization.
Full description
Bulgarian National Audit Office
, issued in 2014
Risk cases: 3
The Swedish Transport Administrations support to research and innovation
Robust internal control required to manage innovations The Swedish agency dealing with transport innovations did not use sufficient control over its research funds, shows the audit of the Swedish National Audit Office. The deficiencies include risk analysis, administrative procedures and management of taxpayers' money.
Full description
Robust internal control required to manage innovations The Swedish agency dealing with transport innovations did not use sufficient control over its research funds, shows the audit of the Swedish National Audit Office. The deficiencies include risk analysis, administrative procedures and management of taxpayers' money.
Full description
Swedish National Audit Office
, issued in 2018
Risk cases: 3
Management of Police Information Resources
Police tasks of the necessary data are processed departmental registers, information systems, automated data processing systems and networks where information is stored, processed and transferred ... to the classified information. The police department has all of these information resources, so the audit focused on the activities and actions of the Department to ensure planning and organizing of the recourses ... , monitoring, evaluation and coordination and other aspects of registers and IS strategic management. The audited period was 2012-2014. For the analysis, there were used previous data and data of 2015 ... ... Fundamentals of IT organisation ... Review by SAI Lithuania makes readers aware that nowadays it is difficult to develop a larger IT system without whole conceptual infrastracture: planning composed into strategy of the organisation ... and well understood architecture of information. Well functioning IT management structures, which on the other hand may sound trivial, were proved here as the key to success.
Full description
Police tasks of the necessary data are processed departmental registers, information systems, automated data processing systems and networks where information is stored, processed and transferred ... to the classified information. The police department has all of these information resources, so the audit focused on the activities and actions of the Department to ensure planning and organizing of the recourses ... , monitoring, evaluation and coordination and other aspects of registers and IS strategic management. The audited period was 2012-2014. For the analysis, there were used previous data and data of 2015 ... ... Fundamentals of IT organisation ... Review by SAI Lithuania makes readers aware that nowadays it is difficult to develop a larger IT system without whole conceptual infrastracture: planning composed into strategy of the organisation ... and well understood architecture of information. Well functioning IT management structures, which on the other hand may sound trivial, were proved here as the key to success.
Full description
National Audit Office of the Republic of Lithuania
, issued in 2015
Risk cases: 4
Homelessness
Homelessness grows despite increased spendings to reduce it British NAO analyses the root-causes of unsuccessful effort to reduce homelessness in England. They point at a side effect of the Goverment reform of welfare reform and at lack of full impact assessment.
Full description
Homelessness grows despite increased spendings to reduce it British NAO analyses the root-causes of unsuccessful effort to reduce homelessness in England. They point at a side effect of the Goverment reform of welfare reform and at lack of full impact assessment.
Full description
National Audit Office
, issued in 2016
Risk cases: 3
Housing in England: overview
Efforts to support housing Even if housebuilding in England has not kept pace with need and there has been a reduction in social rented homes, significant advantages can be enjoyed: an increase in home ownership and in the number of private rented homes. The quality of housing improved in recent years too. The National Audit Office has reviewed critical elements of the housing being one of the government's key priorities. Looking for risks, they found that a potential conflict of objectives can lead to tensions in delivery.
Full description
Efforts to support housing Even if housebuilding in England has not kept pace with need and there has been a reduction in social rented homes, significant advantages can be enjoyed: an increase in home ownership and in the number of private rented homes. The quality of housing improved in recent years too. The National Audit Office has reviewed critical elements of the housing being one of the government's key priorities. Looking for risks, they found that a potential conflict of objectives can lead to tensions in delivery.
Full description
National Audit Office
, issued in 2017
Risk cases: 2
Use of consultants and temporary staff
New skills needed in a longer term UK NAO: Used well, consultants and temporary staff can be an important source of specialist skills and capabilities that are uneconomic for departments to maintain in their permanent staff. Since 2009-10, the government has used spending controls to reduce its use of consultants and temporary staff, and by 2014-15 spending had fallen by £1.5 billion. However, spending has increased by between £400 million and £600 million since 2011-12, suggesting that this was more of a short-term reduction than a sustainable strategy. In the longer term, departments will need to develop workforce, skills and capacity plans to reduce their dependence on external skills. They will need to improve their strategic workforce planning to determine where they can deploy existing staff, where they need to recruit, and where they need to engage temporary resources. Without this, departments cannot demonstrate that they are achieving value for money from the use of consultants and temporary staff.
Full description
New skills needed in a longer term UK NAO: Used well, consultants and temporary staff can be an important source of specialist skills and capabilities that are uneconomic for departments to maintain in their permanent staff. Since 2009-10, the government has used spending controls to reduce its use of consultants and temporary staff, and by 2014-15 spending had fallen by £1.5 billion. However, spending has increased by between £400 million and £600 million since 2011-12, suggesting that this was more of a short-term reduction than a sustainable strategy. In the longer term, departments will need to develop workforce, skills and capacity plans to reduce their dependence on external skills. They will need to improve their strategic workforce planning to determine where they can deploy existing staff, where they need to recruit, and where they need to engage temporary resources. Without this, departments cannot demonstrate that they are achieving value for money from the use of consultants and temporary staff.
Full description
National Audit Office
, issued in 2016
Risk cases: 7
The protection of research data at the Danish universities
The protection of research data at the Danish universities It is Rigsrevisionen’s assessment that the five largest universities are not adequately protecting their research data against unknown IT equipment. As a result, foreign actors may relatively easy gain unauthorized access to the universities’ research data.This is not considered satisfactory by Rigsrevisionen. The study shows that the five largest universities have defined guidelines for researchers’ use of software and hardware centrally, but that they have failed to centralise efforts to maintain a satisfactory level of security for research data. This is due mainly to the fact that, at some universities, researchers are allowed to bring their own devices,and at all the universities, researchers are allowed to have local administrator privileges, which gives them access to install software. Additionally, all five universities know of incidents where unknown hardware has been connected to their network.
Full description
The protection of research data at the Danish universities It is Rigsrevisionen’s assessment that the five largest universities are not adequately protecting their research data against unknown IT equipment. As a result, foreign actors may relatively easy gain unauthorized access to the universities’ research data.This is not considered satisfactory by Rigsrevisionen. The study shows that the five largest universities have defined guidelines for researchers’ use of software and hardware centrally, but that they have failed to centralise efforts to maintain a satisfactory level of security for research data. This is due mainly to the fact that, at some universities, researchers are allowed to bring their own devices,and at all the universities, researchers are allowed to have local administrator privileges, which gives them access to install software. Additionally, all five universities know of incidents where unknown hardware has been connected to their network.
Full description
National Audit Office of Denmark
, issued in 2018
Risk cases: 3
Higher education institutions' provision of premises- room for improvement
How to pay for higher education institutions' premises Higher education institutions' rental costs constitute a significant part of central government rental expenses. Swedish NAO analysed results of reform, which aimed at more effective use of resources at central government agencies and more effective management of real property and assets for the State as a whole. Apart from the positive results as a whole, substantial room for improvement still exists: especially in identifying targets of costs, looking for incentives and in mitigating commercial approach to education institutions.
Full description
How to pay for higher education institutions' premises Higher education institutions' rental costs constitute a significant part of central government rental expenses. Swedish NAO analysed results of reform, which aimed at more effective use of resources at central government agencies and more effective management of real property and assets for the State as a whole. Apart from the positive results as a whole, substantial room for improvement still exists: especially in identifying targets of costs, looking for incentives and in mitigating commercial approach to education institutions.
Full description
Swedish National Audit Office
, issued in 2018
Risk cases: 2
FEMA Needs to Address Management Weaknesses to Improve Its Systems
Controls in emergency management GAO audited the agency of the Department of Homeland Security, responsible for federal efforts to mitigate, respond to, and recover from disasters. American auditors recommend that the agency fully define its investment board’s roles and responsibilities and procedures for selecting and overseeing investments, update its strategic plan and complete plans for IT modernization, and establish time frames for completing workforce planning efforts. The agency should also establish policies and guidance for implementing key IT management controls.
Full description
Controls in emergency management GAO audited the agency of the Department of Homeland Security, responsible for federal efforts to mitigate, respond to, and recover from disasters. American auditors recommend that the agency fully define its investment board’s roles and responsibilities and procedures for selecting and overseeing investments, update its strategic plan and complete plans for IT modernization, and establish time frames for completing workforce planning efforts. The agency should also establish policies and guidance for implementing key IT management controls.
Full description
General Accountability Office
, issued in 2016
Risk cases: 4
Improved Planning and Performance Measures Are Needed to Help Ensure Successful Technology Modernization
Massive modernization effort needs coordination Social security issues can touch lives of many. Information technology in this area are increasingly costly and difficult to maintain. GAO is recommending to develop comprehensive metrics to effectively gauge modernization progress; complete comprehensive strategic planning, including its enterprise architecture; and define the new roles and responsibilities to help ensure effective oversight.
Full description
Massive modernization effort needs coordination Social security issues can touch lives of many. Information technology in this area are increasingly costly and difficult to maintain. GAO is recommending to develop comprehensive metrics to effectively gauge modernization progress; complete comprehensive strategic planning, including its enterprise architecture; and define the new roles and responsibilities to help ensure effective oversight.
Full description
General Accountability Office
, issued in 2012
Risk cases: 3