Effectiveness of development of broadband network or high-speed internet
The National Audit Office audited whether the state has made every effort to ensure that everyone can have unlimited access to fast internet connection by 2020. The National Audit Office also ... analysed whether the network of fibre-optical cables or the basic broadband network, which is built with European Union support and should guarantee high-speed internet connection, has helped to achieve ... this goal. ... ... ... Slower broadband paid by customers ... and institutions. Private companies have not entirely met the Government's expectations. The Estonian SAI has looked for an answer: Why? ... The Estonian Information Society Development Plan foresees that high-speed internet of 30 Mbit/s should be accessible to all people in Estonia by 2020 and that 60% of the population will be using ... superfast internet of over 100 Mbit/s. To achieve these goals, the state, with the help of European Union support, decided to establish a broadband network which is not further than 1.5 km from 98% of homes
Full description
National Audit Office of Estonia , issued in 2015
Risk cases: 3
Management and implementation of 1BestariNet
), State Educations Departments and 50 Government Schools and Government Aided Schools in and around the Central Zone (Kuala Lumpur, Putrajaya, State of Selangor and Perak), Northern Zone (State of Kedah ... 1BestariNet Service Project (1BestariNet) is an initiative undertaken by the Malaysian Ministry of Education (MOE) to replace and enhance ICT connectivity in schools. It is an enhancement ... to the SchoolNet service which terminated on 31 December 2010 with emphasis on end-to-end solutions (E2E) network services together with Virtual Learning Environment (VLE). Under this project, 10,000 primary ... ... To answer big risks in IT systems development you need all levels of organisation ... Audit of 1BestariNet is presented by the Malaysian National Audit Department together with other IT projects reviewed. A result is this concise and instructive list of lessons learnt and failures ... to be avoided. To maximize performance and minimize vendor lock-in you need a lot of concerted effort by top and line management, as well as users ready to work with new tools.
Full description
National Audit Department of Malaysia , issued in 2013
Risk cases: 4
Homeland Security. Oversight of Neglected Human Resources Information Technology Investment Is Needed
Human resources IT investments get stuck in management's lack of interest Although the Human Resources Information Technology (HRIT) investment was initiated about 12 years ago with the intent to consolidate, integrate, and modernize the department's human resources IT infrastructure, the Department of Homeland Security (DHS) has made very limited progress in achieving these goals. HRIT's minimally involved executive steering committee during a time when significant problems were occurring was a key factor in the lack of progress. This is particularly problematic given that the department's ability to efficiently and effectively carry out its mission is significantly hampered by its fragmented human resources. DHS's ineffective management of HRIT, such as the lack of an updated schedule and a life-cycle cost estimate, also contributed to the neglect this investment has experienced. DHS will be limited in efficiently tracking and reporting accurate, comprehensive performance and learning management data across the organization, and could risk further implementation delays.
Full description
US Government Accountability Office , issued in 2016
Risk cases: 1
Steps Needed to Identify Acquisition Training Needs for Non-Acquisition Personnel
Non-Acquisition staff can be crucial for acquisition Despite from hundreds of billions of dollars spent annually to acquire products and services, the US Department of Defense does not full information about staff to be trained. The information is needed about the non-acquisition staff, who can play crucial role in particular acquisitions. As GAO underlines, their identification is necessary to fully understand the training needs and... budget.
Full description
US Government Accountability Office , issued in 2019
Risk cases: 4
Opportunities Exist for FAA to Improve Airport Terminal Area Safety Efforts
Inefficient use of data The US GAO examined various issues related to runway safety and to update its prior work on airport terminal areas. Their findings point at inefficient use of data, which may lead to more risk and to inefficient targeting their limited resources.
Full description
US Government Accountability Office , issued in 2019
Risk cases: 3
Electronic Health Records - VA Needs to Identify and Report Existing System Costs
Difficulties after 30 years of decentralized development The US Department of Veterans Affairs provides health care services to approximately 9 million veterans and their families. However, the IT system they use is more than 30 years old, is costly to maintain, and does not fully support exchanging health data. The US GAO, analyzed the system's modenization plans and found serious problems with definition and cost estimation.
Full description
US Government Accountability Office , issued in 2019
Risk cases: 3
VA ACQUISITION MANAGEMENT: Supply Chain Management and COVID-19 Response
Pandemic points up weaknesses of procurement solutions US Department of Veterans Affairs acquires hundreds of millions of dollars-worth of medical supplies each year. The Medical-Surgical Prime Vendor-Next Generation (MSPV-NG) is one of its key initiatives to modrnize its processes. GAO auditor pointed in their previous audits that the approach lacked an effective medical supply procurement strategy, clinician involvement, and reliable data systems. In time of the pandemic, the problem seems even more difficult to deal with.
Full description
US Government Accountability Office , issued in 2019
Risk cases: 4
RURAL BROADBAND DEPLOYMENT: Improved Consistency with Leading Practices Could Enhance Management of Loan and Grant Programs
Green Book can help in broadband development US GAO applied its COSO based Green Book to review consistency of support programs for rural information infrastructure.
Full description
US Government Accountability Office , issued in 2017
Risk cases: 7
Broadband: Observations on Past and Ongoing Efforts to Expand Access and Improve Mapping Data
Successful broadband delivery with challenges Review of the GAO audits concerned with broadband deployment, expecially across areas where costs are high and returns on the investment are low.
Full description
US Government Accountability Office , issued in 2020
Risk cases: 5
ACQUISITION REFORM: DOD Should Streamline Its Decision-Making Process for Weapon Systems to Reduce Inefficiencies
Refinement of decision-making processes The US Department of Defense (DOD) has long sought to improve the efficiency of its weapon system acquisition process, including the time and effort needed to complete the milestone decision process. Good practices of some DOD programs and five commercial firms were used by GAO to look for new momentum in refining the process.
Full description
US Government Accountability Office , issued in 2015
Risk cases: $risks.size()