General and Creation Control of the Information Systems of the Ministry of Foreign Affairs
achieved considerable progress in the management of the information systems. The auditors reviewed and assessed all key elements of the process. ... The objective of the audit was to assess general and creation control of the information systems of the Ministry of Foreign Affairs. Since the beginning of 2009, the Ministry of Foreign Affairs has ... Overview of problems - area by area ... SAI Lithuania looked into all critical elements of a Ministry's information system, starting from IT architecture, through information security to automation of data processing.
Full description
achieved considerable progress in the management of the information systems. The auditors reviewed and assessed all key elements of the process. ... The objective of the audit was to assess general and creation control of the information systems of the Ministry of Foreign Affairs. Since the beginning of 2009, the Ministry of Foreign Affairs has ... Overview of problems - area by area ... SAI Lithuania looked into all critical elements of a Ministry's information system, starting from IT architecture, through information security to automation of data processing.
Full description
National Audit Office of the Republic of Lithuania
, issued in 2013
Risk cases: 4
The Ministry of the Environment lacks a compact information system and still uses 125 separate information systems and databases
The objective of the audit was to scrutinise the management of funds earmarked for the purchase and administration of ICT within the MoE and selected organisations which come under the management ... chapter of the MoE, through a state co-funded organisation CENIA which comes under the management of the MoE; (3) utilisation of the information systems. The audited period was 2010 to 2013; where relevant ... of the MoE. The audit identified the following risks: (1) non-existence of the Integrated environmental information system (IEIS) as an independent information system; (2) purchase of ICT, within the budget ... ... Ministry of the Environment manages 125 information systems and databases ... The Ministry of the Environment (MoE) has for more than 20 years a legal obligation to administer and manage an Integrated Environmental Information System (IEIS). In spite of this fact, the existing ... systems (more than 125 information systems and databases) are designed, implemented and managed as individual information systems without a direct integration into a joint point of reference.
Full description
The objective of the audit was to scrutinise the management of funds earmarked for the purchase and administration of ICT within the MoE and selected organisations which come under the management ... chapter of the MoE, through a state co-funded organisation CENIA which comes under the management of the MoE; (3) utilisation of the information systems. The audited period was 2010 to 2013; where relevant ... of the MoE. The audit identified the following risks: (1) non-existence of the Integrated environmental information system (IEIS) as an independent information system; (2) purchase of ICT, within the budget ... ... Ministry of the Environment manages 125 information systems and databases ... The Ministry of the Environment (MoE) has for more than 20 years a legal obligation to administer and manage an Integrated Environmental Information System (IEIS). In spite of this fact, the existing ... systems (more than 125 information systems and databases) are designed, implemented and managed as individual information systems without a direct integration into a joint point of reference.
Full description
Supreme Audit Office of Czech Republic
, issued in 2015
Risk cases: 7
Extract from the report to the Public Accounts Committee on the access to IT systems that support the provision of essential services to the Danish society
The report is focused on the significant risk that is associated with inadequate management and control of domain administrator privileges, which makes it possible for unauthorized persons to obtain ... access to the IT systems and data of the institutions. Rigsrevisionen has not examined for what specific purposes unauthorized access to the institutions’ systems and data can be used. ... ... Inadequate management and control of domain administrator privileges ... The Danish report concerns the measures - taken by six government institutions of various branches of State activities - to protect IT systems and data that support the provision of essential ... services to the Danish society from unauthorized access, obtained on the basis of domain administrator privileges.
Full description
The report is focused on the significant risk that is associated with inadequate management and control of domain administrator privileges, which makes it possible for unauthorized persons to obtain ... access to the IT systems and data of the institutions. Rigsrevisionen has not examined for what specific purposes unauthorized access to the institutions’ systems and data can be used. ... ... Inadequate management and control of domain administrator privileges ... The Danish report concerns the measures - taken by six government institutions of various branches of State activities - to protect IT systems and data that support the provision of essential ... services to the Danish society from unauthorized access, obtained on the basis of domain administrator privileges.
Full description
National Audit Office of Denmark
, issued in 2015
Risk cases: 4
Federal Agencies Need to Address Aging Legacy Systems
Be aware of legacy IT risks The US government spends about 75 percent of the total amount budgeted for information technology on operations and maintenance. GAO reviewed Office of Management and Budget and 26 agencies, covering years 2010 through 2017 and recommends to develop a goal for spending measure and finalize guidance to identify and prioritize legacy IT needing to be modernized or replaced.
Full description
Be aware of legacy IT risks The US government spends about 75 percent of the total amount budgeted for information technology on operations and maintenance. GAO reviewed Office of Management and Budget and 26 agencies, covering years 2010 through 2017 and recommends to develop a goal for spending measure and finalize guidance to identify and prioritize legacy IT needing to be modernized or replaced.
Full description
General Accountability Office
, issued in 2016
Risk cases: 3
Information security work at nine agencies
Difficulties in achieving appropriate IT security Together with the Swedish NAO we assume that the picture that emerges at the agencies audited applies also to most of the other agencies in the public administration. The information security work is not given high enough priority in relation to the risks that exist. This applies to both the Government, which should have been clearer in its directions to agencies on this matter, and to agency managements, which did not give priority to the work of information security to the extent required. Much indicates that it is difficult for many agencies to achieve an appropriate level of information security work.
Full description
Difficulties in achieving appropriate IT security Together with the Swedish NAO we assume that the picture that emerges at the agencies audited applies also to most of the other agencies in the public administration. The information security work is not given high enough priority in relation to the risks that exist. This applies to both the Government, which should have been clearer in its directions to agencies on this matter, and to agency managements, which did not give priority to the work of information security to the extent required. Much indicates that it is difficult for many agencies to achieve an appropriate level of information security work.
Full description
Swedish National Audit Office
, issued in 2016
Risk cases: 4
Federal Institute for Risk Assessment purchased unnecessary software
Risk of poor requirements management The Germamn SAI audited the Federal Institute for Risk Assessment that introduce a new software. Time of implementation was nearly three times as long as originally scheduled. The costs also nearly trebled. Moreover, the Institute purchased unnecessary licences for expanding the software
Full description
Risk of poor requirements management The Germamn SAI audited the Federal Institute for Risk Assessment that introduce a new software. Time of implementation was nearly three times as long as originally scheduled. The costs also nearly trebled. Moreover, the Institute purchased unnecessary licences for expanding the software
Full description
Bundesrechnungshof
, issued in 2017
Risk cases: 2
The Swedish Transport Administrations support to research and innovation
Robust internal control required to manage innovations The Swedish agency dealing with transport innovations did not use sufficient control over its research funds, shows the audit of the Swedish National Audit Office. The deficiencies include risk analysis, administrative procedures and management of taxpayers' money.
Full description
Robust internal control required to manage innovations The Swedish agency dealing with transport innovations did not use sufficient control over its research funds, shows the audit of the Swedish National Audit Office. The deficiencies include risk analysis, administrative procedures and management of taxpayers' money.
Full description
Swedish National Audit Office
, issued in 2018
Risk cases: 3
Audit of the procurement of ICT products with the potential to be standard products
ICT procurement system reviewed SFAO points out what is critical in ICT procurement. Requirements management is extremely important, as well as procurement strategies for relevant product groups. Legal rules should protect investments and support competition, but they can still be insufficient without appropriate reporting - if you want your system to adapt to changes.
Full description
ICT procurement system reviewed SFAO points out what is critical in ICT procurement. Requirements management is extremely important, as well as procurement strategies for relevant product groups. Legal rules should protect investments and support competition, but they can still be insufficient without appropriate reporting - if you want your system to adapt to changes.
Full description
Swiss Federal Audit Office
, issued in 2015
Risk cases: 4
Correlations between the operational risks of companies in the majority ownership of local governments and the financial situation of the local governments
Risks related to local governments-owned companies The Hungarian SAI analysed four risk areas, taking 19 aspects and the specificities of Hungary’s settlement patterns into consideration. The four areas defined were the following: performance of public tasks, exercise of proprietary rights, financial stability of local governments, and short and medium-term stability of the financial management of companies.
Full description
Risks related to local governments-owned companies The Hungarian SAI analysed four risk areas, taking 19 aspects and the specificities of Hungary’s settlement patterns into consideration. The four areas defined were the following: performance of public tasks, exercise of proprietary rights, financial stability of local governments, and short and medium-term stability of the financial management of companies.
Full description
State Audit Office of Hungary
, issued in 2017
Risk cases: 1
Insufficient monitoring of consultancy work in large-scale IT projects
Insufficient monitoring of consultancy work in large-scale IT projects The German Federal Ministry of the Interior did not sufficiently plan, monitor and control consultancy work in two large-scale IT projects, not being thus able to evaluate the amount of work done and pay accordingly. It was recommended by SAI the establishment of a quality management system and its application mandatory for large-scale IT projects
Full description
Insufficient monitoring of consultancy work in large-scale IT projects The German Federal Ministry of the Interior did not sufficiently plan, monitor and control consultancy work in two large-scale IT projects, not being thus able to evaluate the amount of work done and pay accordingly. It was recommended by SAI the establishment of a quality management system and its application mandatory for large-scale IT projects
Full description
Bundesrechnungshof
, issued in 2017
Risk cases: 1