Use of consultants and temporary staff
New skills needed in a longer term UK NAO: Used well, consultants and temporary staff can be an important source of specialist skills and capabilities that are uneconomic for departments to maintain in their permanent staff. Since 2009-10, the government has used spending controls to reduce its use of consultants and temporary staff, and by 2014-15 spending had fallen by £1.5 billion. However, spending has increased by between £400 million and £600 million since 2011-12, suggesting that this was more of a short-term reduction than a sustainable strategy. In the longer term, departments will need to develop workforce, skills and capacity plans to reduce their dependence on external skills. They will need to improve their strategic workforce planning to determine where they can deploy existing staff, where they need to recruit, and where they need to engage temporary resources. Without this, departments cannot demonstrate that they are achieving value for money from the use of consultants and temporary staff.
Full description
National Audit Office , issued in 2016
Risk cases: 7
The Swedish Transport Administrations support to research and innovation
Robust internal control required to manage innovations The Swedish agency dealing with transport innovations did not use sufficient control over its research funds, shows the audit of the Swedish National Audit Office. The deficiencies include risk analysis, administrative procedures and management of taxpayers' money.
Full description
Swedish National Audit Office , issued in 2018
Risk cases: 3
Actions of national and municipal authorities to ensure the fulfillment of the obligations under the Loan Agreement “Safety Net and Social Sector Reform Program” between the Republic of Latvia and the World Bank
The audit was planned and conducted so as to provide reasonable assurance that the national and municipal authorities have implemented the measures specified in the Program Document and ensured ... the fulfilment of the prescribed performance targets. ... ... Well coordinated information structure is necessary for the unemployment benefits system ... SAI Latvia reviewed the unemployment benefits system and analyzed the cosequences of poor information flow among state and municipalities registers. Findings presented in the report are result ... of effective use of CAAT software.
Full description
State Audit Office of Latvia , issued in 2011
Risk cases: 1
Management and development of IT systems in the Ministry of the Environment
The purpose of this audit was to assess whether the information systems in the area of government of the Ministry of the Environment (and their development) support the reliable, economical ... and sustainable collection and use of environmental information. On a broader scale the National Audit Office looked at all of the 42 environmental information systems created in the area of government ... of the Ministry of Environment, but focused in greater detail on four of them: the Environmental Register, the Estonian Nature Information System, the Environmental Permits Information System and the Land Cadastre ... ... Estonian environmental information system needs reforms ... Correctness and reliability of the environmental data is guaranteed to a considerable extent. However there is a need for redevelopment of environmental information systems, particularly ... by the Environmental Register.
Full description
National Audit Office of Estonia , issued in 2013
Risk cases: 2
Auditing the National Rationing System
The audit was to investigate the data quality, validity and reliability of two sub-systems (Ration Card and Ration Distribution) of a National Rationing System (Ration System) with the comparison ... to the rules and regulations in order to make an assessment of soundness of the Ration system and its related operations. ... Unreliable databases trigger all kinds of possible problems ... Ministry responsible for functioning of the National Rationing System developed to automate and optimize the delivery of essential subsidized commodities to eligible beneficiaries and providing state ... with reliable information fails its job.
Full description
State Audit Bureau of Kuwait , issued in 2014
Risk cases: 4
IT Police Systems
Implementation by the Polish Police of two IT projects (E-police station and Command Support System - CSS) was audited. Both systems were to relieve the Police officers and increase the quality ... and effectiveness of their work. Audit explained the reason of failure in the case of E-police station project and success in the case of CSS. Although some irregularities occurred in both cases, careful planning ... and organization of the project turned out to make the difference. Accordance with the public procurement law was not part of the audit as a separate investigation in that matter was carried by respective Polish ... ... A textbook example of how not to implement the IT projects ... Polish NIK compared the implementation of two flagship IT projects of the Police HQ: successful 'Command Support System' and problematic 'E-police station'. List of interesting problems appeared...
Full description
Supreme Audit Office of Poland , issued in 2013
Risk cases: 5
Cost-intensive data centres stood idle for years
Idle data centres As found by the German SAI, some of costly Federal data centres stood largely idle. The Ministry failed to adequately assess the project risks. The Ministry needs to avoid similar shortcomings in the proposed federal IT consolidation project.
Full description
Bundesrechnungshof , issued in 2016
Risk cases: 1
Performance Audit of the Georgian Government electronic Procurement system
State procurement is one of the key components of public financial management. Its share in state budget is approximately 25 percent. Effective management of state procurements is an important sphere ... of interest for the State Audit Office. Considering the fact that since 2010 major part of public procurements is being conducted electronically and there is no alternative tool, uninterrupted provision ... of a high-quality service has a particular importance. <br /> It is noteworthy that establishment of open, transparent and competitive environment for the procurement parties mitigates the risks of corruption ... ... Electronic procurement system - how effective are management and control mechanisms? ... SAI Georgia analyzed the electronic Government Procurement system. In their report they focus on compliance and security problems, which may harm the business goals and overall mission of the system.
Full description
State Audit Office Of Georgia , issued in 2016
Risk cases: 5
VAT risk assessment - better use made of information generated by inspections on company premise
Tax inspections may add up to the VAT risk assessment, but... The audit by the German BRH shows that general tax inspections on company premises can also reveal facts that may be relevant for VAT risk assessment. 'However, this information cannot be adequately used for VAT risk assessment because it is not available in electronic format.'
Full description
Bundesrechnungshof , issued in 2016
Risk cases: 1
Audit of the Government, Government-guaranteed and Municipal Debt Management Information Systems in the Ministry of Finance of the Republic of Bulgaria
The main audit question studied during the audit was: Are the government, government-guaranteed (SDMS) and municipal debt management information systems (CMDR) at the Ministry of Finance effective ... ? The audit covered the period from 01.01.2013 to 31.12.2013 and investigated four major areas: IT system strategy and general management; IT security and controls against disasters; Operational controls ... and Documentation; Application Controls. ... ... Even effective and modern IT systems require improvements and updates to ensure their security and accountability ... For the management of the government, government-guaranteed and municipal debt the Ministry of Finance has established an advanced integrated information infrastructure. According to Bulgarian SAI ... the established system is effective and provides updated, complete and correct information. Nevertheless the audit report points out areas of security, application controls as well as documentation as the subjects ... that need further improvement and optimization.
Full description
Bulgarian National Audit Office , issued in 2014
Risk cases: 3