Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
158 results found in 14 ms Page 14 of 16
Open Data Trend Report 2015
How to activate the open data policy The Dutch SAI looks for ways to improve open data practice in the Netherlands. They point at experience of two leading countries: UK and US, and advise to: prepare a concrete action plan, to increase number of mandatory published data, to develop government-wide data inventory and to put open data to work.
Full description
Netherlands Court of Audits , issued in 2015
Risk cases: 4
Improving government’s planning and spending framework
Value for money vs. short-term planning NAO reviewed the UK government's progress in improving their planning and spending framework. The auditors found that the complex structure and lack of longer term perspective in planning form a significant obstacle to fully benefit from the framework.
Full description
National Audit Office , issued in 2018
Risk cases: 7
Homelessness
Homelessness grows despite increased spendings to reduce it British NAO analyses the root-causes of unsuccessful effort to reduce homelessness in England. They point at a side effect of the Goverment reform of welfare reform and at lack of full impact assessment.
Full description
National Audit Office , issued in 2016
Risk cases: 3
Opportunities Exist for FAA to Improve Airport Terminal Area Safety Efforts
Inefficient use of data The US GAO examined various issues related to runway safety and to update its prior work on airport terminal areas. Their findings point at inefficient use of data, which may lead to more risk and to inefficient targeting their limited resources.
Full description
US Government Accountability Office , issued in 2019
Risk cases: 3
Good Practice in Annual Reports 2016-17
Reporting: a real skill The Building Public Trust Awards, sponsored by PwC, have been running for 15 years and the British NAO co-sponsors the public sector award. The Good Practices in annual reports 2016-2017 present eye-opening examples of how to make complex reports easily understandable and how to clearly outline goals and achievement of them.
Full description
National Audit Office , issued in 2018
Risk cases: 4
Broadband: Observations on Past and Ongoing Efforts to Expand Access and Improve Mapping Data
Successful broadband delivery with challenges Review of the GAO audits concerned with broadband deployment, expecially across areas where costs are high and returns on the investment are low.
Full description
US Government Accountability Office , issued in 2020
Risk cases: 5
The rural broadband programme
Intervention in a noncompetitive market The British NAO's audit report of 2013 concerns ambitious yet delayed UK government programme, which objective was to have the best superfast broadband network in Europe by 2015. The report focuses on one of the programme's main problems: rural areas, where commercial providers had no plans to invest, because of lower returns.
Full description
National Audit Office , issued in 2013
Risk cases: 7
The Swedish Transport Administrations support to research and innovation
Robust internal control required to manage innovations The Swedish agency dealing with transport innovations did not use sufficient control over its research funds, shows the audit of the Swedish National Audit Office. The deficiencies include risk analysis, administrative procedures and management of taxpayers' money.
Full description
Swedish National Audit Office , issued in 2018
Risk cases: 3
The Annual Municipal Accounts as a basis for comparing municipalities - are the cost indicator reliable?
Municipal accounting: more standardized or more controlled Municipalities report among others, their costs, which cannot be directly attributed to any specific activity, product, or service. Standardized taxonomies exist, but they are not applied uniformly. Swedish NAO traces ramifications: lower ability to compare municipalities' data and need of more central level control.
Full description
Swedish National Audit Office , issued in 2018
Risk cases: 3
The Art of Governing – the Government’s management of cultural sector institutions
The Art of Influencing cultural institutions Cultural sector is characterised by a large number of small government agencies, companies, foundations and a large diversity of operational forms. Governments may then have problems with the risk of conflicting goals.
Full description
Swedish National Audit Office , issued in 2019
Risk cases: 5
previous 158 results found. Page 14 of 16 next