Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
61 results found in 9 ms Page 5 of 7
Coordinated Audit on Information Technology Governance
IT governance needs awareness and SAIs' support The OLACEFS auditors found that the greatest challenge for the SAIs is to raise the awareness of the audit institutions about the importance of IT governance and the benefits that could be obtained by improving its degree of maturity. The audit was conducted by 11 SAIs and coordinated by TCU of Brasil. They concluded: 'It is important, even urgent, to invest resources to implement or enhance: the IT committees; the IT planning process; strategic IT planning; monitoring the IT contracting process; the business continuity plan; the designation of a responsible person or unit to manage security information; a risk management process; an asset inventory process; an information security committee; and a policy for access control.'
Full description
Latin American andCaribbean Organization of Supreme Audit Institutions , issued in 2015
Risk cases: 5
Whether Disclosure of the Public Sector Data Is Ensured
Strategy more important than declarations Why open data are so dificult to become reality? Lithuania possesses the elements required to disclose data but lacks a strategic approach. The report by SAI Lithuania reviews all critical elements of this problem. Most of them look like a pattern reproduced by other countries. And one important thing: the SAI Lithuania opened their own data - exactly on the day of publication of the audit report!
Full description
National Audit Office of the Republic of Lithuania , issued in 2016
Risk cases: 9
The BBC’s understanding of its audiences and users
Understand your audience, BBC Audience data and insights are critical to the success of broadcasters - which is also true in the case of the world renowned British Broadcasting Corporation. Auditors reviewed the BBC's main projects and the analyst team dedicated to collect and interpret the audience related information. Data coherence, review of performance and benefits traicing - belong to key areas in need of substantial refinements.
Full description
National Audit Office , issued in 2019
Risk cases: 6
Improving broadband
Lessons of Superfast Programme UK NAO's report on goverments extensive support to the superfast internet, with special focus on the Future Programme perspectives. Influence of the COVID-19 pandemic considered.
Full description
National Audit Office , issued in 2020
Risk cases: 7
Staff scheduling in government institutions
Scheduling irregular hours work Danish Rigsrevisionen shows in their study problems with staff scheduling in government institutions where employees are required to work irregular hours. Optimized staff scheduling contributed to reducing payroll costs. On the other hand, problems with rearrangement of work, recording working hours, optimisation of staffing levels and analysis of overtime triggers - add up to high costs of workforce. IT is not always used as ally either.
Full description
National Audit Office of Denmark , issued in 2015
Risk cases: 5
Does the Public Investment in Internet Access Reach the Population?
Middle mile network is not enough Latvia is known for its high-speed Internet provided to individuaals and business. Auditors verified results of the Government's effort to strengthen national infrastructure in this regard. They ponted at issues in: planning, risk analysis, information flow, quality and impact.
Full description
State Audit Office of the Republic of Latvia , issued in 2020
Risk cases: 6
VA ACQUISITION MANAGEMENT: Supply Chain Management and COVID-19 Response
Pandemic points up weaknesses of procurement solutions US Department of Veterans Affairs acquires hundreds of millions of dollars-worth of medical supplies each year. The Medical-Surgical Prime Vendor-Next Generation (MSPV-NG) is one of its key initiatives to modrnize its processes. GAO auditor pointed in their previous audits that the approach lacked an effective medical supply procurement strategy, clinician involvement, and reliable data systems. In time of the pandemic, the problem seems even more difficult to deal with.
Full description
US Government Accountability Office , issued in 2019
Risk cases: 4
Has Public Administration Used All Opportunities for Efficient Management of ICT Infrastructure?
Efficient Management of ICT Infrastructure Centralised management of ICT services and infrastructure would allow the institutions to optimise in long run their resources – financial, human, material and technical. However, we observed during the audit that the move towards ICT centralisation and single data centres has ceased. The different ministries and even the institutions subordinated to the same ministry do not cooperate sufficiently with each other regarding the ICT management, maintenance, and infrastructure placement. They rather choose to maintain their own, sometimes even several, data centres.
Full description
State Audit Office of the Republic of Latvia , issued in 2019
Risk cases: 3
Central government staff costs
Results of staff reductions The British NAO found that departments had significantly reduced numbers of their civil servants and of course salary costs at the same time. But they reduced staff numbers mainly by minimising recruitment, and the age profile of the civil service has changed. NAO pays a lot attention to what effect this has had on the future pipeline of talent and skills. It reminds also that the departments need long-term operating models to work efficiently with the staff reduced.
Full description
National Audit Office , issued in 2015
Risk cases: 5
Building and Implementing the Phoenix Pay System
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Office of theAuditor Generalof Canada , issued in 2018
Risk cases: 3
previous 61 results found. Page 5 of 7 next