45
results found in
11 ms
Page 2
of 5
The rural broadband programme
Intervention in a noncompetitive market The British NAO's audit report of 2013 concerns ambitious yet delayed UK government programme, which objective was to have the best superfast broadband network in Europe by 2015. The report focuses on one of the programme's main problems: rural areas, where commercial providers had no plans to invest, because of lower returns.
Full description
Intervention in a noncompetitive market The British NAO's audit report of 2013 concerns ambitious yet delayed UK government programme, which objective was to have the best superfast broadband network in Europe by 2015. The report focuses on one of the programme's main problems: rural areas, where commercial providers had no plans to invest, because of lower returns.
Full description
National Audit Office
, issued in 2013
Risk cases: 7
Conflicts of interest
First, recognise the conflicts of interest are a real risk the British NAO gathered a significant amount of intelligence on conflicts, particularly in the health and education sectors. These are areas of government where services are increasingly commissioned and delivered by parties at arm’s-length to departments. Conflicts of interest can occur naturally as a product of the way a system is designed and most often arise from operational situations.
Full description
First, recognise the conflicts of interest are a real risk the British NAO gathered a significant amount of intelligence on conflicts, particularly in the health and education sectors. These are areas of government where services are increasingly commissioned and delivered by parties at arm’s-length to departments. Conflicts of interest can occur naturally as a product of the way a system is designed and most often arise from operational situations.
Full description
National Audit Office
, issued in 2015
Risk cases: 8
Centralisation of support services of state authorities
Most goals of centralisation of support services were achived Centralisation of support services of state authorities has generally been successful, the quality of accounting has improved, and accounting has become more effective. The objective of saving on costs was not achieved. It would be beneficial to analyse the implementation of a similar model in local governments, i.e. concentrating the accounting services to central units in order to improve the quality of accounting and make work more effective. It would allow saving working time on doing routine accounting procedures and use this time more for financial management, which helps to use public funds better and more expediently.
Full description
Most goals of centralisation of support services were achived Centralisation of support services of state authorities has generally been successful, the quality of accounting has improved, and accounting has become more effective. The objective of saving on costs was not achieved. It would be beneficial to analyse the implementation of a similar model in local governments, i.e. concentrating the accounting services to central units in order to improve the quality of accounting and make work more effective. It would allow saving working time on doing routine accounting procedures and use this time more for financial management, which helps to use public funds better and more expediently.
Full description
National Audit Office of Estonia
, issued in 2018
Risk cases: 2
State funds spent on development, operation and using of data centres services
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
Supreme Audit Office of Czech Republic
, issued in 2015
Risk cases: 7
Use of consultants and temporary staff
New skills needed in a longer term UK NAO: Used well, consultants and temporary staff can be an important source of specialist skills and capabilities that are uneconomic for departments to maintain in their permanent staff. Since 2009-10, the government has used spending controls to reduce its use of consultants and temporary staff, and by 2014-15 spending had fallen by £1.5 billion. However, spending has increased by between £400 million and £600 million since 2011-12, suggesting that this was more of a short-term reduction than a sustainable strategy. In the longer term, departments will need to develop workforce, skills and capacity plans to reduce their dependence on external skills. They will need to improve their strategic workforce planning to determine where they can deploy existing staff, where they need to recruit, and where they need to engage temporary resources. Without this, departments cannot demonstrate that they are achieving value for money from the use of consultants and temporary staff.
Full description
New skills needed in a longer term UK NAO: Used well, consultants and temporary staff can be an important source of specialist skills and capabilities that are uneconomic for departments to maintain in their permanent staff. Since 2009-10, the government has used spending controls to reduce its use of consultants and temporary staff, and by 2014-15 spending had fallen by £1.5 billion. However, spending has increased by between £400 million and £600 million since 2011-12, suggesting that this was more of a short-term reduction than a sustainable strategy. In the longer term, departments will need to develop workforce, skills and capacity plans to reduce their dependence on external skills. They will need to improve their strategic workforce planning to determine where they can deploy existing staff, where they need to recruit, and where they need to engage temporary resources. Without this, departments cannot demonstrate that they are achieving value for money from the use of consultants and temporary staff.
Full description
National Audit Office
, issued in 2016
Risk cases: 7
The information system of the Public Real Estate Registry does not enable the recording of data in a completely efficient manner
Users to be involved SAI Serbia analysed the Public Real Estate Registry. Starting from missing involvement of users, primary goals of the project were not met. Key issues regarding data input and access are discussed in the text.
Full description
Users to be involved SAI Serbia analysed the Public Real Estate Registry. Starting from missing involvement of users, primary goals of the project were not met. Key issues regarding data input and access are discussed in the text.
Full description
State Audit Institution
, issued in 2019
Risk cases: 3
Improving broadband
Lessons of Superfast Programme UK NAO's report on goverments extensive support to the superfast internet, with special focus on the Future Programme perspectives. Influence of the COVID-19 pandemic considered.
Full description
Lessons of Superfast Programme UK NAO's report on goverments extensive support to the superfast internet, with special focus on the Future Programme perspectives. Influence of the COVID-19 pandemic considered.
Full description
National Audit Office
, issued in 2020
Risk cases: 7
Software Developement Effective Practices and Federal Chalenges in Applying Agile Methods
To identify effective practices in applying Agile for software developement solutions and federal challenges in implementing Agile techniques. ... Agile project approach in government practice ... Useful products delivered in a short time are basis for often applauded features of agile project approach. Applied by many private companies, it tends as well to be more and more popular among state ... administrations. American GAO reviewed set of agile projects and revealed - apart from advantages - a set of commonly occurring problems: poor team work, lack of time and deficit of customers’ trust.
Full description
To identify effective practices in applying Agile for software developement solutions and federal challenges in implementing Agile techniques. ... Agile project approach in government practice ... Useful products delivered in a short time are basis for often applauded features of agile project approach. Applied by many private companies, it tends as well to be more and more popular among state ... administrations. American GAO reviewed set of agile projects and revealed - apart from advantages - a set of commonly occurring problems: poor team work, lack of time and deficit of customers’ trust.
Full description
General Accountability Office
, issued in 2012
Risk cases: 4
Effectiveness of the Tax Administration of the Republic of Slovenia in the execution of modernisation projects of the Slovenian duty information system and decreasing the number of duty sub-accounts
The Tax Administration of the Republic of Slovenia (hereinafter: the Tax Administration) is responsible for collecting taxes, fees and other compulsory levies (hereinafter: duties ... ). These are the revenue of the state budget, municipal budgets, the Health Insurance Institute of Slovenia, the Institute for Pension and Disability Insurance of Slovenia (hereinafter: duties recipients) and indirectly ... of the European Union budget. In order to improve its operations, the Tax Authority decided to modernise the Slovenian duties’ collection information system. It used this opportunity to implement also a second ... ... Shaky coordination of investments in important systems ... Slovenian SAI traced a series of problems in management of crucial IT investments in tax administration. Apart from promising goals, unclear business case gave a start to many problems at next stages ... of the project, involving additional spendings, delays and errors in data processing.
Full description
The Tax Administration of the Republic of Slovenia (hereinafter: the Tax Administration) is responsible for collecting taxes, fees and other compulsory levies (hereinafter: duties ... ). These are the revenue of the state budget, municipal budgets, the Health Insurance Institute of Slovenia, the Institute for Pension and Disability Insurance of Slovenia (hereinafter: duties recipients) and indirectly ... of the European Union budget. In order to improve its operations, the Tax Authority decided to modernise the Slovenian duties’ collection information system. It used this opportunity to implement also a second ... ... Shaky coordination of investments in important systems ... Slovenian SAI traced a series of problems in management of crucial IT investments in tax administration. Apart from promising goals, unclear business case gave a start to many problems at next stages ... of the project, involving additional spendings, delays and errors in data processing.
Full description
Court of Audit of the Republic of Slovenia
, issued in 2014
Risk cases: 7
The Public Web Sites During a Period of Transmission to e-Government
Websites of e-Transformation Turkish auditors bring back their audit of 2006, in which they, among others reveiwed public websites during a period of transmission to e-Governmentbasics of the e-Transformation project.
Full description
Websites of e-Transformation Turkish auditors bring back their audit of 2006, in which they, among others reveiwed public websites during a period of transmission to e-Governmentbasics of the e-Transformation project.
Full description
Turkish Court of Accounts
, issued in 2006
Risk cases: 6