90
results found in
12 ms
Page 4
of 9
Public access point to the Polish e-Administration
Coordinated audit series (46 auditees) focused on a web solution applied to give an easy access to Government e-services (the project planned to be completed in 2013) The audit was performed in 2008 ... and public report issued in March 2009. Primary goal of th presentation was intended to illustrate the use of 'e-Government Algorithm' elaborated by EUROSAI IT Working Group in 2005. One of issues mede better ... known by the audit was 'Project Frameworks vs Public Procurement'. ... ... Buyer, provider and methodologies need a balance ... Presentation based on a vast audit by Polish SAI which subject was of big network project aiming to provide one access point to Government and Selfgovernments services. The presentation illustrates ... old EUROSAI IT Wg 'Algorithm approach' and focuses on procurement systemic problems.
Full description
Coordinated audit series (46 auditees) focused on a web solution applied to give an easy access to Government e-services (the project planned to be completed in 2013) The audit was performed in 2008 ... and public report issued in March 2009. Primary goal of th presentation was intended to illustrate the use of 'e-Government Algorithm' elaborated by EUROSAI IT Working Group in 2005. One of issues mede better ... known by the audit was 'Project Frameworks vs Public Procurement'. ... ... Buyer, provider and methodologies need a balance ... Presentation based on a vast audit by Polish SAI which subject was of big network project aiming to provide one access point to Government and Selfgovernments services. The presentation illustrates ... old EUROSAI IT Wg 'Algorithm approach' and focuses on procurement systemic problems.
Full description
Supreme Audit Office of Poland
, issued in 2008
Risk cases: 3
Lessons learned from government ICT-projects
This audit has been performed on request of the Dutch parliament. Some newspapers mentioned government losses of four to five billion euro's on a yearly bases. These news items caused the parliament ... to request this audit. The audit has been performed in only 5 months time and consisted of the re-use of earlier performed audits. We have 'recycled' earlier findings about ICT-projects. ... 'Expensive' does not always mean 'High Quality', so... do not feed the spiral ... Excellent analysis of systemic errors commited when designing Government IT projects. The report aims at the essence of problems which are encountered far from information technologies - in: politics ... , business, psychology... Do not be mislead by date of report, it is evergreen for all who really want to know why IT projects fail.
Full description
This audit has been performed on request of the Dutch parliament. Some newspapers mentioned government losses of four to five billion euro's on a yearly bases. These news items caused the parliament ... to request this audit. The audit has been performed in only 5 months time and consisted of the re-use of earlier performed audits. We have 'recycled' earlier findings about ICT-projects. ... 'Expensive' does not always mean 'High Quality', so... do not feed the spiral ... Excellent analysis of systemic errors commited when designing Government IT projects. The report aims at the essence of problems which are encountered far from information technologies - in: politics ... , business, psychology... Do not be mislead by date of report, it is evergreen for all who really want to know why IT projects fail.
Full description
Netherlands Court of Audits
, issued in 2007
Risk cases: 3
IT Support in the Judicial Chain
The Swedish National Audit Office has examined how well agencies in the judicial chain have handled known flaws in their IT support and whether the Government’s control mechanisms have provided ... the agencies with sufficient prerequisites to expand and improve IT support. ... ... Needed: good conditions by government, better steering and control by authorities ... Despite many years’ of work to modernize the IT support within the judiciary, there are still many deficiencies. The Government has not given the authorities good conditions enough to lead the work ... . The authorities, in their turn, need to improve their steering and control, as well as interact to a much higher degree.
Full description
The Swedish National Audit Office has examined how well agencies in the judicial chain have handled known flaws in their IT support and whether the Government’s control mechanisms have provided ... the agencies with sufficient prerequisites to expand and improve IT support. ... ... Needed: good conditions by government, better steering and control by authorities ... Despite many years’ of work to modernize the IT support within the judiciary, there are still many deficiencies. The Government has not given the authorities good conditions enough to lead the work ... . The authorities, in their turn, need to improve their steering and control, as well as interact to a much higher degree.
Full description
Swedish National Audit Office
, issued in 2011
Risk cases: 3
Copyright Office Needs to Develop Plans that Address Technical and Organizational Challenges
The mission of the Copyright Office, a service unit within the Library of Congress, is to promote creativity by administering and sustaining a national copyright system. As part of this mission ... , the Copyright Office registers about 500,000 creative works a year for copyright and records documentation related to copyright transfer and sale. In recent years, the Register of Copyrights has discussed ... the need for a modernized Copyright Office, to include upgrades to the current IT environment. ... No justified investments without IT strategy ... GAO shows in its report on the US Copyright Office, what is a role of IT strategy in organisaion. Effects can be found at the bottom and at the top: the lack of strategic plan can make it more ... difficult to solve practical problems, but it can also put the overall mission of the Office at risk.
Full description
The mission of the Copyright Office, a service unit within the Library of Congress, is to promote creativity by administering and sustaining a national copyright system. As part of this mission ... , the Copyright Office registers about 500,000 creative works a year for copyright and records documentation related to copyright transfer and sale. In recent years, the Register of Copyrights has discussed ... the need for a modernized Copyright Office, to include upgrades to the current IT environment. ... No justified investments without IT strategy ... GAO shows in its report on the US Copyright Office, what is a role of IT strategy in organisaion. Effects can be found at the bottom and at the top: the lack of strategic plan can make it more ... difficult to solve practical problems, but it can also put the overall mission of the Office at risk.
Full description
General Accountability Office
, issued in 2015
Risk cases: 2
Coordination of Infrastructure Works by Metropolitan Municipalities
Rapid population growth at metropoles as well as dense and planless structuring, especially in İstanbul and Ankara, have lead to an increase in demand for utilities services and consequently ... , in the resources used for the construction and maintenance of utilities. Moreover, in cities with dense population, damages to roads and sidewalks during the construction and maintenance of utilities cause problems ... in daily life, create financial burden and necessitate effective solutions. The purpose of this audit is to ensure that metropolitan municipalities eradicate defects in implementation, and Ministry ... ... ... Start geographic information system with cooperation rules and digital maps ... Organization of geographic and infrastructure information systems is an especially difficult task when bacause vast and intense coordination is necessary. The Turkisch Court of Accounts lists ... problems that reduce use and rise costs of this fundamental task.
Full description
Rapid population growth at metropoles as well as dense and planless structuring, especially in İstanbul and Ankara, have lead to an increase in demand for utilities services and consequently ... , in the resources used for the construction and maintenance of utilities. Moreover, in cities with dense population, damages to roads and sidewalks during the construction and maintenance of utilities cause problems ... in daily life, create financial burden and necessitate effective solutions. The purpose of this audit is to ensure that metropolitan municipalities eradicate defects in implementation, and Ministry ... ... ... Start geographic information system with cooperation rules and digital maps ... Organization of geographic and infrastructure information systems is an especially difficult task when bacause vast and intense coordination is necessary. The Turkisch Court of Accounts lists ... problems that reduce use and rise costs of this fundamental task.
Full description
Turkish Court of Accounts
, issued in 2008
Risk cases: 2
The implementation of national IT projects in social and health care
IT management expenditure in public administration totalled about 2.1 billion euros in 2009. IT management expenditure by local authorities and federations of municipalities in the field of health ... care totalled about 270 million euros ino 2009. Health care's share of IT management expenditure in public administration thus amounted to about 13 per cent in 2009. ... ... IT-centred manner of project implementation can harm IT investments' results ... SAI Finland perfomed a vast review of IT projects in health and social protection. Many interesting findings cover structural problems, as 'Many separate systems with no future' and characteristics ... of poor governance, as 'No cost monitoring - unclear objectives - arguable usefulness'.
Full description
IT management expenditure in public administration totalled about 2.1 billion euros in 2009. IT management expenditure by local authorities and federations of municipalities in the field of health ... care totalled about 270 million euros ino 2009. Health care's share of IT management expenditure in public administration thus amounted to about 13 per cent in 2009. ... ... IT-centred manner of project implementation can harm IT investments' results ... SAI Finland perfomed a vast review of IT projects in health and social protection. Many interesting findings cover structural problems, as 'Many separate systems with no future' and characteristics ... of poor governance, as 'No cost monitoring - unclear objectives - arguable usefulness'.
Full description
National Audit Office of Finland
, issued in 2011
Risk cases: 3
The development and use of identification services in public administration
The audit examined the implementation and coordination of projects aimed at developing identification services in public administration, cooperation among authorities in this area and compliance ... with legislation in procuring services. The audit also examined development, control and monitoring structures regarding identification services. The audit focused on electronic identification services that are used ... in public administration's electronic transactions. ... ... Unhealthy competition linked with lack of coordinatnion and with procurement irregularities ... See what may go wrong with the IT public procurement. Check out what is the basis to avoid irregularities or omissions in complying with public procurement legislation. National Audit Office ... of Finland identified also risks resulting from lack of horizontal coordination.
Full description
The audit examined the implementation and coordination of projects aimed at developing identification services in public administration, cooperation among authorities in this area and compliance ... with legislation in procuring services. The audit also examined development, control and monitoring structures regarding identification services. The audit focused on electronic identification services that are used ... in public administration's electronic transactions. ... ... Unhealthy competition linked with lack of coordinatnion and with procurement irregularities ... See what may go wrong with the IT public procurement. Check out what is the basis to avoid irregularities or omissions in complying with public procurement legislation. National Audit Office ... of Finland identified also risks resulting from lack of horizontal coordination.
Full description
National Audit Office of Finland
, issued in 2008
Risk cases: 3
State funds spent on development, operation and using of data centres services
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction.
Full description
Supreme Audit Office of Czech Republic
, issued in 2015
Risk cases: 7
Preparations and realization of the State A-levels
The aim of the audit was to scrutinise the utilisation of the state budget and EU budget funds that had been spent on preparing and implementing the State A-levels examinations. The auditing ... operation was performed from May to November 2011. The audited period extended from January 1, 2005, to June 30, 2011; where relevant, the data from the previous period and the period until the end ... of the auditing operation were also scrutinized. Among the audited bodies were the Ministry of Education, the Education Result Survey Centre, and the National Institute for Further Education. The auditing operation ... ... Begin with good strategy ... Analyzing problems of state examinations system, Czech Republic SAI found that commonplace strategy effected in shortsighted planning, poor procurement and disadvantageous contracting.
Full description
The aim of the audit was to scrutinise the utilisation of the state budget and EU budget funds that had been spent on preparing and implementing the State A-levels examinations. The auditing ... operation was performed from May to November 2011. The audited period extended from January 1, 2005, to June 30, 2011; where relevant, the data from the previous period and the period until the end ... of the auditing operation were also scrutinized. Among the audited bodies were the Ministry of Education, the Education Result Survey Centre, and the National Institute for Further Education. The auditing operation ... ... Begin with good strategy ... Analyzing problems of state examinations system, Czech Republic SAI found that commonplace strategy effected in shortsighted planning, poor procurement and disadvantageous contracting.
Full description
Supreme Audit Office of Czech Republic
, issued in 2011
Risk cases: 4
Audit on the broadband internet infrastructure access
Poland has been granted over PLN 4 billion from the European Regional Development Fund to build the broadband internet access infrastructure. As part of three operational programmes 90 percent ... of assumed financing was contracted, namely PLN 3.9 billion. By the end of 2015, Poland should complete the investment and account for the expenses. According to NIK there is a risk that the infrastructure ... construction will not be completed by the deadline and the EU funds may not be used to the full. ... ... Simpler regulations and better supervision needed ... Polish SAI audited a project, which aim had been to develop broadband internet network across the country. They revealed that legal obstacles, idleness and lack of supervision were the main causes ... of delays. Some of the projects are in danger of not being completed on time and some of the EU funds may not be fully used.
Full description
Poland has been granted over PLN 4 billion from the European Regional Development Fund to build the broadband internet access infrastructure. As part of three operational programmes 90 percent ... of assumed financing was contracted, namely PLN 3.9 billion. By the end of 2015, Poland should complete the investment and account for the expenses. According to NIK there is a risk that the infrastructure ... construction will not be completed by the deadline and the EU funds may not be used to the full. ... ... Simpler regulations and better supervision needed ... Polish SAI audited a project, which aim had been to develop broadband internet network across the country. They revealed that legal obstacles, idleness and lack of supervision were the main causes ... of delays. Some of the projects are in danger of not being completed on time and some of the EU funds may not be fully used.
Full description
Supreme Audit Office of Poland
, issued in 2015
Risk cases: 2