Identifying and meeting central government's skills requirements
Start with well managed responsibilities UK Departments have invested heavily in skills development. Government estimates that expenditure on formal training, including salary costs of departmental learning and development staff, was £275 million in 2009-10. NAO identified weaknesses of the system which start with devolved responsibilities, lead to: weak data, mis-profiled trainings, doubtful personal decisions, lack of well-targeted evaluation - and finish at more expensive buying-in and retaining key skills...
Full description
National Audit Office , issued in 2011
Risk cases: 6
Management of IT security in systems outsourced to external suppliers
Security to be improved in IT processes outsourced to external suppliers When IT processes are outsourced to external suppliers, the authorities no longer have direct control of the IT security, but remain responsible for managing the security of the IT. Authorities that fail to manage IT security actively based on risk assessments, and omit to monitor the implementation of these requirements, will not be able to determine if the level of IT security in the outsourced systems safeguards their systems and data. This is how the conclusion of the Rigsrevisionen starts. The Danish auditors noticed improvement in the audited entities, but they add that tha majority of the auditees: can refine their requirements for and follow-up on access control and logging practices
Full description
National Audit Office of Denmark , issued in 2016
Risk cases: 3
Management of State Information Resources
The objective of the audit was to assess effectiveness of the management of the state information resources and of the use of their possibilities: suitability of the chosen state resources management ... model; rationality of the use of the State Budget funds when managing information resources; use of the possibilities of the state information resources to improve the performance of the public sector ... . Audit procedures were performed in all major institutions which form and implement the policy of information resources: Ministry of Transport and Communications, Ministry of the Interior, Ministry ... Well targeted requirements, interconnected information resources and broad use - why so difficult to be gained? ... The leading idea of the 'Approach to Management of State Information Resources' programme was to entrench a comprehensive management of data resources. After five years preparations, the desired ... momentum was still not the case. SAI Lithuania analysed roots of the problems: concept, poor use of funds, lack of interconnections, unsatified users.
Full description
National Audit Office of the Republic of Lithuania , issued in 2013
Risk cases: 3
Performance Audit of Public Debt Management Information Systems
of information systems in the public debt management process and having considered legal requirements to information security, State Audit Office of Georgia conducted Performance Audit of Public Debt Management ... The usage and development of the information technologies in public financial management is an important priority of the country at the phase of intensive implementation of electronic governance ... of Georgia. <br/> In the framework of the forehead mentioned audit, SAOG decided to initiate an IT audit of the MOF information systems used in Public Debt Management. The Audit was focused on Public Debt ... ... More effective IT governance needed ... Importance of effective performance of public debt management e-systems may be explained by the world’s increased dependence on such systems. In parallel with the performance audit of debt management ... financial institutions. Audit conducted by the State Audit Office of Georgia has revealed security and governance shortcomings related to management and usage of these systems. ... information systems of the Ministry Of Finance of Georgia, Supreme Audit Institutions of 11 countries also studied this topic, both in terms of systems’ performance and their practical application by local
Full description
State Audit Office Of Georgia , issued in 2014
Risk cases: 5
VA ACQUISITION MANAGEMENT: Supply Chain Management and COVID-19 Response
Pandemic points up weaknesses of procurement solutions US Department of Veterans Affairs acquires hundreds of millions of dollars-worth of medical supplies each year. The Medical-Surgical Prime Vendor-Next Generation (MSPV-NG) is one of its key initiatives to modrnize its processes. GAO auditor pointed in their previous audits that the approach lacked an effective medical supply procurement strategy, clinician involvement, and reliable data systems. In time of the pandemic, the problem seems even more difficult to deal with.
Full description
US Government Accountability Office , issued in 2019
Risk cases: 4
Federal Institute for Risk Assessment purchased unnecessary software
Risk of poor requirements management The Germamn SAI audited the Federal Institute for Risk Assessment that introduce a new software. Time of implementation was nearly three times as long as originally scheduled. The costs also nearly trebled. Moreover, the Institute purchased unnecessary licences for expanding the software
Full description
Bundesrechnungshof , issued in 2017
Risk cases: 2
Audit of the procurement of ICT products with the potential to be standard products
ICT procurement system reviewed SFAO points out what is critical in ICT procurement. Requirements management is extremely important, as well as procurement strategies for relevant product groups. Legal rules should protect investments and support competition, but they can still be insufficient without appropriate reporting - if you want your system to adapt to changes.
Full description
Swiss Federal Audit Office , issued in 2015
Risk cases: 4
Electronic Records. Management and Preservation Pose Challenges
Basics of electronic records management This audit of GAO, reported in 2003, can be helpful in looking for basic problems in electronic records management. These problems are compounded as computer hardware, application software, and even storage media become obsolete, as they may leave behind electronic records that can no longer be read.
Full description
General Accountability Office , issued in 2003
Risk cases: 7
The National Offender Management Information System (NOMIS)
for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... Rescoping necessary, but not fully successful ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits.
Full description
National Audit Office , issued in 2009
Risk cases: 4
FEMA Needs to Address Management Weaknesses to Improve Its Systems
Controls in emergency management GAO audited the agency of the Department of Homeland Security, responsible for federal efforts to mitigate, respond to, and recover from disasters. American auditors recommend that the agency fully define its investment board’s roles and responsibilities and procedures for selecting and overseeing investments, update its strategic plan and complete plans for IT modernization, and establish time frames for completing workforce planning efforts. The agency should also establish policies and guidance for implementing key IT management controls.
Full description
General Accountability Office , issued in 2016
Risk cases: 4