Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
122 results found in 13 ms Page 11 of 13
Operation of the Record Systems Applied in the Eligibility Scheme of Benefits and Services Provided from the Social Security Funds
Hungarian SAI evaluated the set-up and operation of the basic registries of managing bodies (National Health Insurance Fund, Central Administration of National Pension Insurance, National Tax ... and Customs Administration), as well as the dataflow amongst them. In addition, the control system of fulfilling the data provision obligation was evaluated, as well as the IT support activities and whether ... the records had proven reliable in supporting services in compliance with eligibilities and in filtering unjustified services. The audited period covered the years 2007-2010. ... ... Well considered regulations are essential for good quality data ... State Audit Office of Hungary.has proved that date safety may depend on quality of regulations. The report on record systems of social security services casted light on risk connected with huge data ... bases managed by different entities, in a changing legal environment.
Full description
State Audit Office of Hungary , issued in 2012
Risk cases: 2
Traffic Ticketing information system
The audit included two areas of focus - the environment surrounding the Traffic Ticketing Information System - the System (designed to input, process, manage and collect payment for the traffic ... tickets) and also the internal environment of the System that guarantees the quality of its performance and safety. ... Security can hinder effectiveness ... SAI of Kuwait analysed system supporting collection of the traffic tickets - data input, processing and management. What was found was lack of basic safety measures, that hindered the effectiveness ... of the system.
Full description
State Audit Bureau of Kuwait , issued in 2014
Risk cases: 3
Supply of food and medicinal products
Supply of food and medicinal products Deficiencies in emergency preparedness and weaknesses in governance are still found by the Swedish NAO in the system of safeguarding supply of food and medicinal products. The system is complex and NAO appreciates efforts made by responsible agencies. However, they found also insufficient clarity in division of responsibilities and weaknesses in coordinantion.
Full description
Swedish National Audit Office , issued in 2018
Risk cases: 2
The Actıvıtıes Carrıed out wıthın the Framework of e-Transformatıon Turkey Project
'e-Transformation Turkey' Project Turkish SAI report presents a checklist of issues, which were spotted during the large scale e-Government transformation.
Full description
Turkish Court of Accounts , issued in 2006
Risk cases: 4
Audit of the key ICT project federal GEVER programme Federal Chancellery
During the first stage, two new GEVER (electronic records and process management) products were procured in an open WTO tender within the framework of the two-product strategy (federal GEVER WTO ... procurement project). CHF 1.6 million was spent on these. The departments and Federal Chancellery (departments/FCh) had to choose one of the two products within three months of the contract being awarded. ... ... Advanced process management system's cost-effectiveness and deadlines at risk ... Ever since 1990, sequential controls and file management have been part of the Federal Administration's IT landscape (GEVER business administration). Significant obstacles have to be overcome ... in order to ensure the successful creation and introduction of GEVER. Previous efforts did not have any widespread success and led to a diverse GEVER landscape. The federal GEVER project has now laid ... the foundations for simplification and centralisation.
Full description
Swiss Federal Audit Office , issued in 2015
Risk cases: 2
Cost-intensive data centres stood idle for years
Idle data centres As found by the German SAI, some of costly Federal data centres stood largely idle. The Ministry failed to adequately assess the project risks. The Ministry needs to avoid similar shortcomings in the proposed federal IT consolidation project.
Full description
Bundesrechnungshof , issued in 2016
Risk cases: 1
The Ministry of the Environment lacks a compact information system and still uses 125 separate information systems and databases
The objective of the audit was to scrutinise the management of funds earmarked for the purchase and administration of ICT within the MoE and selected organisations which come under the management ... of the MoE. The audit identified the following risks: (1) non-existence of the Integrated environmental information system (IEIS) as an independent information system; (2) purchase of ICT, within the budget ... chapter of the MoE, through a state co-funded organisation CENIA which comes under the management of the MoE; (3) utilisation of the information systems. The audited period was 2010 to 2013; where relevant ... ... Ministry of the Environment manages 125 information systems and databases ... The Ministry of the Environment (MoE) has for more than 20 years a legal obligation to administer and manage an Integrated Environmental Information System (IEIS). In spite of this fact, the existing ... systems (more than 125 information systems and databases) are designed, implemented and managed as individual information systems without a direct integration into a joint point of reference.
Full description
Supreme Audit Office of Czech Republic , issued in 2015
Risk cases: 7
Protection against fraud in migration activities at missions abroad
Migration activities can be a subject to fraud The audit showed that reports on alleged fraud in migration activities at missions abroad increased continually between 2014 and 2017. Altogether about 60 alleged cases of fraud were reported during the period, including selling interview appointments, stolen visa stickers, issuing visas on false grounds and prohibited searches in case management systems. Missions abroad, the Ministry for Foreign Affairs and the Swedish Migration Board are all responsible for migration activities at missions abroad. The division of responsibility between them is sometimes unclear and difficult to assess. According to the Swedish NAO this leads to particular challenges in ensuring satisfactory and common protection against fraud at missions abroad. Ensuring protection is made even more difficult in that the missions abroad vary regarding in terms of size, case volume, case mix and risk exposure. In addition, for the missions abroad the internal control requirements are notsufficiently explicit.
Full description
Swedish National Audit Office , issued in 2018
Risk cases: 2
Homeland Security. Oversight of Neglected Human Resources Information Technology Investment Is Needed
Human resources IT investments get stuck in management's lack of interest Although the Human Resources Information Technology (HRIT) investment was initiated about 12 years ago with the intent to consolidate, integrate, and modernize the department's human resources IT infrastructure, the Department of Homeland Security (DHS) has made very limited progress in achieving these goals. HRIT's minimally involved executive steering committee during a time when significant problems were occurring was a key factor in the lack of progress. This is particularly problematic given that the department's ability to efficiently and effectively carry out its mission is significantly hampered by its fragmented human resources. DHS's ineffective management of HRIT, such as the lack of an updated schedule and a life-cycle cost estimate, also contributed to the neglect this investment has experienced. DHS will be limited in efficiently tracking and reporting accurate, comprehensive performance and learning management data across the organization, and could risk further implementation delays.
Full description
US Government Accountability Office , issued in 2016
Risk cases: 1
The National Offender Management Information System (NOMIS)
This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits.
Full description
National Audit Office , issued in 2009
Risk cases: 4
previous 122 results found. Page 11 of 13 next