Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
16 results found in 10 ms Page 2 of 2
Building and Implementing the Phoenix Pay System
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Office of theAuditor Generalof Canada , issued in 2018
Risk cases: 3
Supply of food and medicinal products
Supply of food and medicinal products Deficiencies in emergency preparedness and weaknesses in governance are still found by the Swedish NAO in the system of safeguarding supply of food and medicinal products. The system is complex and NAO appreciates efforts made by responsible agencies. However, they found also insufficient clarity in division of responsibilities and weaknesses in coordinantion.
Full description
Swedish National Audit Office , issued in 2018
Risk cases: 2
Online fraud
Uneven response to online fraud This type of fraud can affect everyone, but yet it is not a strategic priority for local police forces and the response from industry is uneven. UK NAO underlines: For too long, as a low-value but high-volume crime, online fraud has been overlooked by government, law enforcement and industry. It is a crime that can affect everyone. Fraud is now the most commonly experienced crime in England and Wales, is growing rapidly and demands an urgent response. Yet fraud is not a strategic priority for local police forces, and the response from industry is uneven.
Full description
National Audit Office , issued in 2017
Risk cases: 6
Federal Agencies Need to Address Aging Legacy Systems
Be aware of legacy IT risks The US government spends about 75 percent of the total amount budgeted for information technology on operations and maintenance. GAO reviewed Office of Management and Budget and 26 agencies, covering years 2010 through 2017 and recommends to develop a goal for spending measure and finalize guidance to identify and prioritize legacy IT needing to be modernized or replaced.
Full description
General Accountability Office , issued in 2016
Risk cases: 3
Digital transformation in government
Support exemplars, provide consistent guidance... and do not lose focus As the NAO states: Government faces significant challenges in providing public services. While many government services are now available online, public administration is struggling to manage more complicated programmes and to improve the complex systems and processes that support public services.
Full description
National Audit Office , issued in 2017
Risk cases: 4
GAO-20-701, COVID-19: Federal Efforts Could Be Strengthened by Timely and Concerted Actions
Overview of the response to the COVID-19 The bimonthly GAO report on efforts related to the COVID-19 pandemic examines key actions the federal government. Among others, interesting points: medical supply chain, future vaccine distribution, data collection and cybersecurity.
Full description
US Government Accountability Office , issued in 2020
Risk cases: 6
previous 16 results found. Page 2 of 2