Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
36 results found in 8 ms Page 1 of 4
VETERANS’ HEALTH CARE - Preliminary Observations on VHA’s Claims Processing Delays and Efforts to Improve the Timeliness of Payments to Community Providers
, GAO obtained fiscal year 2015 data on the timeliness of VHA’s, Medicare’s, and TRICARE’s claims processing. GAO visited 4 of 95 VHA claims processing locations (selected on the basis of variation ... in geographic location, performance, and workload); reviewed VHA documents and 156 claims from those 4 locations; and interviewed officials from VHA, Medicare, TRICARE, and selected community providers and state ... hospital associations. Results from GAO’s analysis are not generalizable to all VHA claims processing locations or community providers. GAO shared the information provided in this statement with VHA ... Data processing hold back by technology limitation, workload and administrative burden ... US GAO analyzed all factors of slower processing and user unfriendliness that occur sometimes to the veterans healthcare. The main focus is data processing - and it has been proved that it can ... be failing not only because of technology, but also because of work-process design, staff and organisation.
Full description
General Accountability Office , issued in 2016
Risk cases: 6
Audit of the procurement of ICT products with the potential to be standard products
ICT procurement system reviewed SFAO points out what is critical in ICT procurement. Requirements management is extremely important, as well as procurement strategies for relevant product groups. Legal rules should protect investments and support competition, but they can still be insufficient without appropriate reporting - if you want your system to adapt to changes.
Full description
Swiss Federal Audit Office , issued in 2015
Risk cases: 4
Federal Human Resources Data
Internal control weaknesses may put mission at risk GAO audited the Enterprise Human Resources Integration payroll data warehose. The American auditors pointed at problems that may impede 'leverage of these data to meet its mission and allow others to make full use' of them. The critical internal contols areas to be improved in this cas are: completeness, accuracy, and validity of information, authorization, documentation, monitoring, results' evaluation.
Full description
General Accountability Office , issued in 2016
Risk cases: 2
General and Creation Control of the Information Systems of the Ministry of Foreign Affairs
The objective of the audit was to assess general and creation control of the information systems of the Ministry of Foreign Affairs. Since the beginning of 2009, the Ministry of Foreign Affairs has ... achieved considerable progress in the management of the information systems. The auditors reviewed and assessed all key elements of the process. ... Overview of problems - area by area ... SAI Lithuania looked into all critical elements of a Ministry's information system, starting from IT architecture, through information security to automation of data processing.
Full description
National Audit Office of the Republic of Lithuania , issued in 2013
Risk cases: 4
Whether Disclosure of the Public Sector Data Is Ensured
Strategy more important than declarations Why open data are so dificult to become reality? Lithuania possesses the elements required to disclose data but lacks a strategic approach. The report by SAI Lithuania reviews all critical elements of this problem. Most of them look like a pattern reproduced by other countries. And one important thing: the SAI Lithuania opened their own data - exactly on the day of publication of the audit report!
Full description
National Audit Office of the Republic of Lithuania , issued in 2016
Risk cases: 9
Building and Implementing the Phoenix Pay System
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Office of theAuditor Generalof Canada , issued in 2018
Risk cases: 3
Management and protection of assets in the field of the information-communication technologies at the ME SR
internal and security directives, unidentified critical and strategic Information Systems (IS), absolutely unsatisfying principles, procedures, conditions and policy relating to the data backuping (and ... The Supreme Audit office of the Slovak Republic (SAO SR) has conducted the audit at the Ministry of Environment of the Slovak Republic (ME SR) for the audit period 2011 and 2012 to examine ... the compliance with the generally binding legal regulations and the general statues in the field of the information-communication technologies (ICT) and the information systems of the public administration (ISPA ... ... Started from contracting, ended in security ... The perceptive and filled with findings audit - conducted by the Slovak SAI - discovered the list of issues which started in careless contracting procedures, failure to update the development concept ... and ended in exposing the organization to high security risks.
Full description
Supreme Audit Office of the Slovak Republic , issued in 2012
Risk cases: 4
Electronic Health Records - VA Needs to Identify and Report Existing System Costs
Difficulties after 30 years of decentralized development The US Department of Veterans Affairs provides health care services to approximately 9 million veterans and their families. However, the IT system they use is more than 30 years old, is costly to maintain, and does not fully support exchanging health data. The US GAO, analyzed the system's modenization plans and found serious problems with definition and cost estimation.
Full description
US Government Accountability Office , issued in 2019
Risk cases: 3
Working of Inland Container Depots and Container Freight Stations
NEW! Online report on audit of SAI India With this first digital audit report of the Comptroller and Auditor General of India, new chapter has been opened in our profession: the online form is primary versus printable pdf. Advantages: high level of readability, live responsive charts, easy browsing and search of what users find interesting. The reported performance audit concerned 'dry ports', or multimodal logistics centres, which play growing role in domestic and international trade. It shows how gaps in concept and lax attitude to internal control can result on capacities, speed of trade, and enviromental safety.
Full description
Comptroller and Auditor General of India , issued in 2017
Risk cases: 5
Prevention Activities Against Traffic Accidents
Performance Audit Studies covering certain IT Issues related to Prevention Activities Against Traffic Accidents. It aims to contribute to the continuous improvement of prevention activities against ... traffic accidents, which are dramatically leading to loss of life and property. Examination and evaluation of the Traffic Information Systems (TIS) under the traffic control headline. TIS' main purpose ... is to conduct the traffic control activities efficiently with the help of systematic data. Objective of this audit was to contribute to the continuous improvement of prevention activities against traffic ... ... ... You need a way more than IT, to make an IT system successful ... SAI of Turkey examined the Traffic Information Systems and found out that not only IT infrastructure determined the audited IT project's outcomes. There were also non-IT issues that decided: low ... quality of driving education, poor technical infrastruture, as well as lack of monitoring and coordination at prioritization stage.
Full description
Turkish Court of Accounts , issued in 2008
Risk cases: 4
36 results found. Page 1 of 4 next