Maintenance efficiency in the rail network
The primary objective of railway politics is to contribute to ensure that users of the transport service have good railway options. The Norwegian National Rail Administration is organised under ... the Ministry of Transport and Communications, and its responsibilities include operation, maintenance and development of the State's railway infrastructure. The maintenance activities must safeguard safety ... , fixed assets and operational stability of the railway system. The most important objective for the maintenance is to reduce the scope of operational interruptions, and to facilitate better punctuality ... ... Rail network maintenance - negative balance of costs and results ... part of the examined period, from 2006 to 2011. It turned positive from 2011, but in 2014 results were still worse than in 2006. The results have lagged behind the Ministry's target figures for most ... SAI Norway evaluated efficiency of the railway maintenance and found that its costs increased nearly 110 per cent in years 2006–2014. Negative development in uptime and regularity dominated the first ... of the period.
Full description
Office of the Auditor General of Norway , issued in 2016
Risk cases: 2
Analysis of Trends in SAI Japan’s Findings
Analysis of IT audit cases by Board of Audit of Japan in years 2004-12. ... Not used IT systems and overpaid 'ghost' services ... Wrap-up of almost a decade of SAI of Japan's IT related audits results in a form of list of most often found problems. On the top of the list are unwanted or overpaid IT systems and too expensive ... maintanance. It makes you thinking: if one of the world technology leaders could find this, what could we find in our country...
Full description
Board of Audit of Japan , issued in 2014
Risk cases: 3
State funds spent on development, operation and using of data centres services
The aim of the audit was to scrutinise the management of funds spent on building and operating the national data centre (hereinafter “STC1 data centre”), including the expenditure of selected ... organisational units of the state on buying hosting, server-housing and other related services. The audited period was between 2010 and 2014; where relevant, the preceding period was also scrutinised. Audited ... entities: Ministry of the Interior (“MoI”); Ministry of Finance (“MoF”); STÁTNÍ TISKÁRNA CENIN, state firm (state banknote printing firm, hereinafter “STC” or “the state firm”). The audit was conducted ... ... Risks steming from uncoordinated strategy ... was to guard high quality standards for all crucial IT systems in the state administration. Next consecquences were (among others) risk of uneconomical results of large IT investment and risk of inefficient ... supply of services, as well as opposite results of workforce reduction. ... SAI of Czech Republic analysed consequences of failures in strategic IT management at the state level. Lack of coordination and implementation rules reduced practical role of the ministry whose task
Full description
Supreme Audit Office of Czech Republic , issued in 2015
Risk cases: 7
Information Technology Cost Estimation Agencies Need to Address Significant Weakness in Policies and Practices
To estimate reliable cost for the sucess of an IT program by providing the basis for the informed decision making and realistic budget information. To assess the extent to which selected departments ... and agencies have appropriately implement costestimating policies an procedures(four caracteristics of a reliable cost estimation: comprehensive, well-documented, accurate, credible). ... IT cost estimation ... Check out what may go wrong with the information technology cost estimation. Results of the US GAO audit can help to identify high risk areas: comprehensiveness of estimations, their documentation ... , lack of adequacy and inadequate implementation.
Full description
General Accountability Office , issued in 2012
Risk cases: 4
The development and use of identification services in public administration
The audit examined the implementation and coordination of projects aimed at developing identification services in public administration, cooperation among authorities in this area and compliance ... with legislation in procuring services. The audit also examined development, control and monitoring structures regarding identification services. The audit focused on electronic identification services that are used ... in public administration's electronic transactions. ... ... Unhealthy competition linked with lack of coordinatnion and with procurement irregularities ... of Finland identified also risks resulting from lack of horizontal coordination. ... See what may go wrong with the IT public procurement. Check out what is the basis to avoid irregularities or omissions in complying with public procurement legislation. National Audit Office
Full description
National Audit Office of Finland , issued in 2008
Risk cases: 3
The implementation of national IT projects in social and health care
IT management expenditure in public administration totalled about 2.1 billion euros in 2009. IT management expenditure by local authorities and federations of municipalities in the field of health ... care totalled about 270 million euros ino 2009. Health care's share of IT management expenditure in public administration thus amounted to about 13 per cent in 2009. ... ... IT-centred manner of project implementation can harm IT investments' results ... SAI Finland perfomed a vast review of IT projects in health and social protection. Many interesting findings cover structural problems, as 'Many separate systems with no future' and characteristics ... of poor governance, as 'No cost monitoring - unclear objectives - arguable usefulness'.
Full description
National Audit Office of Finland , issued in 2011
Risk cases: 3
State aid for IT projects in social and health care
In 2000-2009 about 180 million euros in national and European Union funds went to finance information technology projects in social and health care, not including the costs of developing national ... information system services (KanTa project) or the National Project for Social Services IT (Tikesos project). Financing has been provided by the Ministry of Social Affairs and H ealth, the Finnish Funding ... Agency for Technology and Innovation (Tekes), regional councils (previously state provincial offices), and indirectly by the Slot Machine Association under the direction of the Ministry of Social Affairs ... Difficult coordination of IT projects ... Finish Audit Office analyzed results of poor cooperation between authorities on national and local level in social and health care projects: difficult integration of information systems and poor ... coordination of the financing information technology projects, including double financing.
Full description
National Audit Office of Finland , issued in 2011
Risk cases: 3
Quality of public services in information society in 2010
. A positive example is registration of a person’s place of residence, which has become considerably easier and user-friendlier than in 2007 as a result of the development of the state portal. <br/> 2007 Audit ... The National Audit Office found that irrespective of a few positive changes, the quality of provision of public services in information society has not improved significantly in comparison to 2007 ... . Information about the services is still difficult to find on websites and people who use public services must still submit unjustified documents, proof of facts or go to administrative agencies in person ... ... The quality of public services has been improved but still isn’t good enough ... Irrespective of a few positive changes, the quality of provision of public services in information society has not improved significantly in comparison to 2007. Information about the services ... is still difficult to find on websites and people who use public services must still submit unjustified documents, proof of facts or go to administrative agencies in person.
Full description
National Audit Office of Estonia , issued in 2010
Risk cases: 2
VETERANS’ HEALTH CARE - Preliminary Observations on VHA’s Claims Processing Delays and Efforts to Improve the Timeliness of Payments to Community Providers
hospital associations. Results from GAO’s analysis are not generalizable to all VHA claims processing locations or community providers. GAO shared the information provided in this statement with VHA ... Due to increases in expenditures and utilization of VA care in the community services in recent years, VHA has had difficulty processing claims in a timely manner. In planning to consolidate its ... existing VA care in the community programs, as required by law, the agency said it will examine strategies for improving the timeliness and accuracy of its payments to community providers.<br ... Data processing hold back by technology limitation, workload and administrative burden ... US GAO analyzed all factors of slower processing and user unfriendliness that occur sometimes to the veterans healthcare. The main focus is data processing - and it has been proved that it can ... be failing not only because of technology, but also because of work-process design, staff and organisation.
Full description
General Accountability Office , issued in 2016
Risk cases: 6
Management and implementation of 1BestariNet
1BestariNet Service Project (1BestariNet) is an initiative undertaken by the Malaysian Ministry of Education (MOE) to replace and enhance ICT connectivity in schools. It is an enhancement ... to the SchoolNet service which terminated on 31 December 2010 with emphasis on end-to-end solutions (E2E) network services together with Virtual Learning Environment (VLE). Under this project, 10,000 primary ... and secondary public schools in Malaysia are equipped with high-speed 4G Internet access and a virtual learning platform, providing high-speed internet connectivity and access to a world-class Integrated Learning ... ... To answer big risks in IT systems development you need all levels of organisation ... Audit of 1BestariNet is presented by the Malaysian National Audit Department together with other IT projects reviewed. A result is this concise and instructive list of lessons learnt and failures ... to be avoided. To maximize performance and minimize vendor lock-in you need a lot of concerted effort by top and line management, as well as users ready to work with new tools.
Full description
National Audit Department of Malaysia , issued in 2013