Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
27 results found in 16 ms Page 1 of 3
Building and Implementing the Phoenix Pay System
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Office of theAuditor Generalof Canada , issued in 2018
Risk cases: 3
FEMA Needs to Address Management Weaknesses to Improve Its Systems
Controls in emergency management GAO audited the agency of the Department of Homeland Security, responsible for federal efforts to mitigate, respond to, and recover from disasters. American auditors recommend that the agency fully define its investment board’s roles and responsibilities and procedures for selecting and overseeing investments, update its strategic plan and complete plans for IT modernization, and establish time frames for completing workforce planning efforts. The agency should also establish policies and guidance for implementing key IT management controls.
Full description
General Accountability Office , issued in 2016
Risk cases: 4
Federal Agencies Need to Address Aging Legacy Systems
Be aware of legacy IT risks The US government spends about 75 percent of the total amount budgeted for information technology on operations and maintenance. GAO reviewed Office of Management and Budget and 26 agencies, covering years 2010 through 2017 and recommends to develop a goal for spending measure and finalize guidance to identify and prioritize legacy IT needing to be modernized or replaced.
Full description
General Accountability Office , issued in 2016
Risk cases: 3
Products sold on the European market: unravelling the system of CE marking
Problems with general picture The Netherlands National Court of Audit was interested in finding out whether anyone keeps track of all the actors involved in the process of system of European Union product markings. The interest was aroused by an observation that the vast majority of the questions raised about the system were prompted by incidents and that the questioners did not generally appear to be interested in the operation of the system as a whole...
Full description
The Netherlands Court of Audit , issued in 2017
Risk cases: 5
Digital transformation in government
Support exemplars, provide consistent guidance... and do not lose focus As the NAO states: Government faces significant challenges in providing public services. While many government services are now available online, public administration is struggling to manage more complicated programmes and to improve the complex systems and processes that support public services.
Full description
National Audit Office , issued in 2017
Risk cases: 4
Conflicts of interest
First, recognise the conflicts of interest are a real risk the British NAO gathered a significant amount of intelligence on conflicts, particularly in the health and education sectors. These are areas of government where services are increasingly commissioned and delivered by parties at arm’s-length to departments. Conflicts of interest can occur naturally as a product of the way a system is designed and most often arise from operational situations.
Full description
National Audit Office , issued in 2015
Risk cases: 8
Performance measurement by regulators
Performance measurement for regulators Primary adressees of this good practice guide - by the British NAO - are regulators, the public institutions established for making sure that an industry or system works legally and fairly. But we are sure that many more can find this guidance useful - including auditors. NAO presents a comprehensible framework for performance measurement and hints how to focus on influence that regulators can use.
Full description
National Audit Office , issued in 2016
Risk cases: 2
Federal Human Resources Data
Internal control weaknesses may put mission at risk GAO audited the Enterprise Human Resources Integration payroll data warehose. The American auditors pointed at problems that may impede 'leverage of these data to meet its mission and allow others to make full use' of them. The critical internal contols areas to be improved in this cas are: completeness, accuracy, and validity of information, authorization, documentation, monitoring, results' evaluation.
Full description
General Accountability Office , issued in 2016
Risk cases: 2
Homeland Security. Oversight of Neglected Human Resources Information Technology Investment Is Needed
Human resources IT investments get stuck in management's lack of interest Although the Human Resources Information Technology (HRIT) investment was initiated about 12 years ago with the intent to consolidate, integrate, and modernize the department's human resources IT infrastructure, the Department of Homeland Security (DHS) has made very limited progress in achieving these goals. HRIT's minimally involved executive steering committee during a time when significant problems were occurring was a key factor in the lack of progress. This is particularly problematic given that the department's ability to efficiently and effectively carry out its mission is significantly hampered by its fragmented human resources. DHS's ineffective management of HRIT, such as the lack of an updated schedule and a life-cycle cost estimate, also contributed to the neglect this investment has experienced. DHS will be limited in efficiently tracking and reporting accurate, comprehensive performance and learning management data across the organization, and could risk further implementation delays.
Full description
US Government Accountability Office , issued in 2016
Risk cases: 1
Electronic Records. Management and Preservation Pose Challenges
Basics of electronic records management This audit of GAO, reported in 2003, can be helpful in looking for basic problems in electronic records management. These problems are compounded as computer hardware, application software, and even storage media become obsolete, as they may leave behind electronic records that can no longer be read.
Full description
General Accountability Office , issued in 2003
Risk cases: 7
27 results found. Page 1 of 3 next