21
results found in
19 ms
Page 1
of 3
Audit of the asset preservation and management activities of state-owned (partly state-owned) economic organisations – HungaroControl Hungarian Air Navigation Services Pte.Ltd.Co.
Compliance review of an air traffic services provider Lack of formal approval of the 2014 annual report was an issue found by Hungarian auditors in HungaroControl, a state-owned company, which provides training for air traffic personnel and carries out air navigation research and development.
Full description
Compliance review of an air traffic services provider Lack of formal approval of the 2014 annual report was an issue found by Hungarian auditors in HungaroControl, a state-owned company, which provides training for air traffic personnel and carries out air navigation research and development.
Full description
State Audit Office of Hungary
, issued in 2017
Risk cases: 1
Federal Agencies Need to Address Aging Legacy Systems
Be aware of legacy IT risks The US government spends about 75 percent of the total amount budgeted for information technology on operations and maintenance. GAO reviewed Office of Management and Budget and 26 agencies, covering years 2010 through 2017 and recommends to develop a goal for spending measure and finalize guidance to identify and prioritize legacy IT needing to be modernized or replaced.
Full description
Be aware of legacy IT risks The US government spends about 75 percent of the total amount budgeted for information technology on operations and maintenance. GAO reviewed Office of Management and Budget and 26 agencies, covering years 2010 through 2017 and recommends to develop a goal for spending measure and finalize guidance to identify and prioritize legacy IT needing to be modernized or replaced.
Full description
General Accountability Office
, issued in 2016
Risk cases: 3
Australian Taxation Office: Administration of Australian Business Number Registrations
More elligibility and data integrity needed The Australian Business Number (ABN) and Australian Business Register initiatives were implemented as part of theGovernment's comprehensive reform of the taxation system in 2000. Their introduction involved challenging issues of technology and governance , including the imperative to process and register significant numbers of applications in a short time. Overall, the Australian SAI concluded that the ABN registration process is operating effectively. However, matters relating to the eligibility of some ABN applicants need to be reviewed. Further, some data integrity issues remain outstanding.
Full description
More elligibility and data integrity needed The Australian Business Number (ABN) and Australian Business Register initiatives were implemented as part of theGovernment's comprehensive reform of the taxation system in 2000. Their introduction involved challenging issues of technology and governance , including the imperative to process and register significant numbers of applications in a short time. Overall, the Australian SAI concluded that the ABN registration process is operating effectively. However, matters relating to the eligibility of some ABN applicants need to be reviewed. Further, some data integrity issues remain outstanding.
Full description
The Australian National Audit Office
, issued in 2003
Risk cases: 3
Central government staff costs
Results of staff reductions The British NAO found that departments had significantly reduced numbers of their civil servants and of course salary costs at the same time. But they reduced staff numbers mainly by minimising recruitment, and the age profile of the civil service has changed. NAO pays a lot attention to what effect this has had on the future pipeline of talent and skills. It reminds also that the departments need long-term operating models to work efficiently with the staff reduced.
Full description
Results of staff reductions The British NAO found that departments had significantly reduced numbers of their civil servants and of course salary costs at the same time. But they reduced staff numbers mainly by minimising recruitment, and the age profile of the civil service has changed. NAO pays a lot attention to what effect this has had on the future pipeline of talent and skills. It reminds also that the departments need long-term operating models to work efficiently with the staff reduced.
Full description
National Audit Office
, issued in 2015
Risk cases: 5
Conflicts of interest
First, recognise the conflicts of interest are a real risk the British NAO gathered a significant amount of intelligence on conflicts, particularly in the health and education sectors. These are areas of government where services are increasingly commissioned and delivered by parties at arm’s-length to departments. Conflicts of interest can occur naturally as a product of the way a system is designed and most often arise from operational situations.
Full description
First, recognise the conflicts of interest are a real risk the British NAO gathered a significant amount of intelligence on conflicts, particularly in the health and education sectors. These are areas of government where services are increasingly commissioned and delivered by parties at arm’s-length to departments. Conflicts of interest can occur naturally as a product of the way a system is designed and most often arise from operational situations.
Full description
National Audit Office
, issued in 2015
Risk cases: 8
Use of consultants and temporary staff
New skills needed in a longer term UK NAO: Used well, consultants and temporary staff can be an important source of specialist skills and capabilities that are uneconomic for departments to maintain in their permanent staff. Since 2009-10, the government has used spending controls to reduce its use of consultants and temporary staff, and by 2014-15 spending had fallen by £1.5 billion. However, spending has increased by between £400 million and £600 million since 2011-12, suggesting that this was more of a short-term reduction than a sustainable strategy. In the longer term, departments will need to develop workforce, skills and capacity plans to reduce their dependence on external skills. They will need to improve their strategic workforce planning to determine where they can deploy existing staff, where they need to recruit, and where they need to engage temporary resources. Without this, departments cannot demonstrate that they are achieving value for money from the use of consultants and temporary staff.
Full description
New skills needed in a longer term UK NAO: Used well, consultants and temporary staff can be an important source of specialist skills and capabilities that are uneconomic for departments to maintain in their permanent staff. Since 2009-10, the government has used spending controls to reduce its use of consultants and temporary staff, and by 2014-15 spending had fallen by £1.5 billion. However, spending has increased by between £400 million and £600 million since 2011-12, suggesting that this was more of a short-term reduction than a sustainable strategy. In the longer term, departments will need to develop workforce, skills and capacity plans to reduce their dependence on external skills. They will need to improve their strategic workforce planning to determine where they can deploy existing staff, where they need to recruit, and where they need to engage temporary resources. Without this, departments cannot demonstrate that they are achieving value for money from the use of consultants and temporary staff.
Full description
National Audit Office
, issued in 2016
Risk cases: 7
Digital transformation in government
Support exemplars, provide consistent guidance... and do not lose focus As the NAO states: Government faces significant challenges in providing public services. While many government services are now available online, public administration is struggling to manage more complicated programmes and to improve the complex systems and processes that support public services.
Full description
Support exemplars, provide consistent guidance... and do not lose focus As the NAO states: Government faces significant challenges in providing public services. While many government services are now available online, public administration is struggling to manage more complicated programmes and to improve the complex systems and processes that support public services.
Full description
National Audit Office
, issued in 2017
Risk cases: 4
Good Practice in Annual Reports 2016-17
Reporting: a real skill The Building Public Trust Awards, sponsored by PwC, have been running for 15 years and the British NAO co-sponsors the public sector award. The Good Practices in annual reports 2016-2017 present eye-opening examples of how to make complex reports easily understandable and how to clearly outline goals and achievement of them.
Full description
Reporting: a real skill The Building Public Trust Awards, sponsored by PwC, have been running for 15 years and the British NAO co-sponsors the public sector award. The Good Practices in annual reports 2016-2017 present eye-opening examples of how to make complex reports easily understandable and how to clearly outline goals and achievement of them.
Full description
National Audit Office
, issued in 2018
Risk cases: 4
Homelessness
Homelessness grows despite increased spendings to reduce it British NAO analyses the root-causes of unsuccessful effort to reduce homelessness in England. They point at a side effect of the Goverment reform of welfare reform and at lack of full impact assessment.
Full description
Homelessness grows despite increased spendings to reduce it British NAO analyses the root-causes of unsuccessful effort to reduce homelessness in England. They point at a side effect of the Goverment reform of welfare reform and at lack of full impact assessment.
Full description
National Audit Office
, issued in 2016
Risk cases: 3
Information security work at nine agencies
Difficulties in achieving appropriate IT security Together with the Swedish NAO we assume that the picture that emerges at the agencies audited applies also to most of the other agencies in the public administration. The information security work is not given high enough priority in relation to the risks that exist. This applies to both the Government, which should have been clearer in its directions to agencies on this matter, and to agency managements, which did not give priority to the work of information security to the extent required. Much indicates that it is difficult for many agencies to achieve an appropriate level of information security work.
Full description
Difficulties in achieving appropriate IT security Together with the Swedish NAO we assume that the picture that emerges at the agencies audited applies also to most of the other agencies in the public administration. The information security work is not given high enough priority in relation to the risks that exist. This applies to both the Government, which should have been clearer in its directions to agencies on this matter, and to agency managements, which did not give priority to the work of information security to the extent required. Much indicates that it is difficult for many agencies to achieve an appropriate level of information security work.
Full description
Swedish National Audit Office
, issued in 2016
Risk cases: 4