Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
4 results found in 3 ms Page 1 of 1
The National Offender Management Information System (NOMIS)
This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits. ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered
Full description
National Audit Office , issued in 2009
Risk cases: 4
The management of the State Property and Funds while Information Systems Building for the Ministry of Defence
The aim of the audit was to examine management during process of extension and modernization of the current information systems and at building of new information systems for the needs ... of the Ministry of Defence or the Army of the Czech Republic. Operating of information systems is inseparably linked with the communication infrastructure, thus the technological shift to ICT was reviewed also ... in this connection. The stationary ICT systems are determined to support management of the Ministry of Defence in period of peace. They are also supposed as a tool of crisis management. The auditing operation covered ... ... Information systems not balanced with infrastructure ... Both organizational changes and inflexibility produce unbalanced plans which cause deiscrepancies between IS and infrastructure.
Full description
Supreme Audit Office , issued in 2005
Risk cases: 2
Software Developement Effective Practices and Federal Chalenges in Applying Agile Methods
To identify effective practices in applying Agile for software developement solutions and federal challenges in implementing Agile techniques. ... Agile project approach in government practice ... Useful products delivered in a short time are basis for often applauded features of agile project approach. Applied by many private companies, it tends as well to be more and more popular among state ... administrations. American GAO reviewed set of agile projects and revealed - apart from advantages - a set of commonly occurring problems: poor team work, lack of time and deficit of customers’ trust.
Full description
General Accountability Office , issued in 2012
Risk cases: 4
IT Police Systems
Implementation by the Polish Police of two IT projects (E-police station and Command Support System - CSS) was audited. Both systems were to relieve the Police officers and increase the quality ... and effectiveness of their work. Audit explained the reason of failure in the case of E-police station project and success in the case of CSS. Although some irregularities occurred in both cases, careful planning ... and organization of the project turned out to make the difference. Accordance with the public procurement law was not part of the audit as a separate investigation in that matter was carried by respective Polish ... ... A textbook example of how not to implement the IT projects ... Polish NIK compared the implementation of two flagship IT projects of the Police HQ: successful 'Command Support System' and problematic 'E-police station'. List of interesting problems appeared...
Full description
Supreme Audit Office of Poland , issued in 2013
Risk cases: 5
4 results found. Page 1 of 1