Federal Human Resources Data
Internal control weaknesses may put mission at risk GAO audited the Enterprise Human Resources Integration payroll data warehose. The American auditors pointed at problems that may impede 'leverage of these data to meet its mission and allow others to make full use' of them. The critical internal contols areas to be improved in this cas are: completeness, accuracy, and validity of information, authorization, documentation, monitoring, results' evaluation.
Full description
General Accountability Office , issued in 2016
Risk cases: 2
Information Technology Cost Estimation Agencies Need to Address Significant Weakness in Policies and Practices
To estimate reliable cost for the sucess of an IT program by providing the basis for the informed decision making and realistic budget information. To assess the extent to which selected departments ... and agencies have appropriately implement costestimating policies an procedures(four caracteristics of a reliable cost estimation: comprehensive, well-documented, accurate, credible). ... IT cost estimation ... Check out what may go wrong with the information technology cost estimation. Results of the US GAO audit can help to identify high risk areas: comprehensiveness of estimations, their documentation ... , lack of adequacy and inadequate implementation.
Full description
General Accountability Office , issued in 2012
Risk cases: 4
Traffic Ticketing information system
The audit included two areas of focus - the environment surrounding the Traffic Ticketing Information System - the System (designed to input, process, manage and collect payment for the traffic ... tickets) and also the internal environment of the System that guarantees the quality of its performance and safety. ... Security can hinder effectiveness ... SAI of Kuwait analysed system supporting collection of the traffic tickets - data input, processing and management. What was found was lack of basic safety measures, that hindered the effectiveness ... of the system.
Full description
State Audit Bureau of Kuwait , issued in 2014
Risk cases: 3
FEMA Needs to Address Management Weaknesses to Improve Its Systems
Controls in emergency management GAO audited the agency of the Department of Homeland Security, responsible for federal efforts to mitigate, respond to, and recover from disasters. American auditors recommend that the agency fully define its investment board’s roles and responsibilities and procedures for selecting and overseeing investments, update its strategic plan and complete plans for IT modernization, and establish time frames for completing workforce planning efforts. The agency should also establish policies and guidance for implementing key IT management controls.
Full description
General Accountability Office , issued in 2016
Risk cases: 4
Improved Planning and Performance Measures Are Needed to Help Ensure Successful Technology Modernization
Massive modernization effort needs coordination Social security issues can touch lives of many. Information technology in this area are increasingly costly and difficult to maintain. GAO is recommending to develop comprehensive metrics to effectively gauge modernization progress; complete comprehensive strategic planning, including its enterprise architecture; and define the new roles and responsibilities to help ensure effective oversight.
Full description
General Accountability Office , issued in 2012
Risk cases: 3
Higher education institutions' provision of premises- room for improvement
How to pay for higher education institutions' premises Higher education institutions' rental costs constitute a significant part of central government rental expenses. Swedish NAO analysed results of reform, which aimed at more effective use of resources at central government agencies and more effective management of real property and assets for the State as a whole. Apart from the positive results as a whole, substantial room for improvement still exists: especially in identifying targets of costs, looking for incentives and in mitigating commercial approach to education institutions.
Full description
Swedish National Audit Office , issued in 2018
Risk cases: 2
Federal Agencies Need to Address Aging Legacy Systems
Be aware of legacy IT risks The US government spends about 75 percent of the total amount budgeted for information technology on operations and maintenance. GAO reviewed Office of Management and Budget and 26 agencies, covering years 2010 through 2017 and recommends to develop a goal for spending measure and finalize guidance to identify and prioritize legacy IT needing to be modernized or replaced.
Full description
General Accountability Office , issued in 2016
Risk cases: 3
General and Creation Control of the Information Systems of the Ministry of Foreign Affairs
The objective of the audit was to assess general and creation control of the information systems of the Ministry of Foreign Affairs. Since the beginning of 2009, the Ministry of Foreign Affairs has ... achieved considerable progress in the management of the information systems. The auditors reviewed and assessed all key elements of the process. ... Overview of problems - area by area ... SAI Lithuania looked into all critical elements of a Ministry's information system, starting from IT architecture, through information security to automation of data processing.
Full description
National Audit Office of the Republic of Lithuania , issued in 2013
Risk cases: 4
Does the state administration effectively use the stored information?
State administration could use the accumulated information more effectively Latvian auditors found that government institutions have a good cooperation in the area of data use, but there are still several areas wherein a person still has to perform the function of a 'courier'. Many channels of data exchange and distribution used in state administration create a fragmented and complicated environment for maintenance of ICT, while responsible ministry does not become actively involved and does not coordinate cooperation of institutions.
Full description
State Audit Office of the Republic of Latvia , issued in 2017
Risk cases: 4
Effectiveness of the Tax Administration of the Republic of Slovenia in the execution of modernisation projects of the Slovenian duty information system and decreasing the number of duty sub-accounts
The Tax Administration of the Republic of Slovenia (hereinafter: the Tax Administration) is responsible for collecting taxes, fees and other compulsory levies (hereinafter: duties ... ). These are the revenue of the state budget, municipal budgets, the Health Insurance Institute of Slovenia, the Institute for Pension and Disability Insurance of Slovenia (hereinafter: duties recipients) and indirectly ... of the European Union budget. In order to improve its operations, the Tax Authority decided to modernise the Slovenian duties’ collection information system. It used this opportunity to implement also a second ... ... Shaky coordination of investments in important systems ... Slovenian SAI traced a series of problems in management of crucial IT investments in tax administration. Apart from promising goals, unclear business case gave a start to many problems at next stages ... of the project, involving additional spendings, delays and errors in data processing.
Full description
Court of Audit of the Republic of Slovenia , issued in 2014
Risk cases: 7