Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
23 results found in 12 ms Page 1 of 3
The Shared Services Centre
The necessary environment for the efficient management of the Shared Service Center is lacking The department's administration of the Shared Services Centre (SSC) has been effective for sharing resources between the departments and delivering selected back-office services to a small client base. However, the governance arrangements established to oversight the SSC have not positioned it well for the future and the departments have not yet determined if the arrangement is efficient and resulting in savings. ANAO found instances where the advisory board of SSC was not consulted or involved in decisions relating to the strategic direction, financial arrangements and expenditure priorities. Information reported to the board did not focus on areas of strategic importance and the quality and completeness of this information could be improved. The mechanisms established for setting out responsibilities and obligations and ensuring transparency for services delivered by the SSC was weak. Service standards and levels were not fixed and can change. The delineation of responsibilities between the SSC and its clients was not clear and there was no commitment by the SSC to certify the quality of its control framework.
Full description
The Australian National Audit Office , issued in 2016
Risk cases: 2
Management and development of IT systems in the Ministry of the Environment
and sustainable collection and use of environmental information. On a broader scale the National Audit Office looked at all of the 42 environmental information systems created in the area of government ... The purpose of this audit was to assess whether the information systems in the area of government of the Ministry of the Environment (and their development) support the reliable, economical ... of the Ministry of Environment, but focused in greater detail on four of them: the Environmental Register, the Estonian Nature Information System, the Environmental Permits Information System and the Land Cadastre ... ... Estonian environmental information system needs reforms ... Correctness and reliability of the environmental data is guaranteed to a considerable extent. However there is a need for redevelopment of environmental information systems, particularly ... by the Environmental Register.
Full description
National Audit Office of Estonia , issued in 2013
Risk cases: 2
The National Government Service Centre – Has administration become more effective?
The purpose of this audit has been to investigate whether the Service Centre has made administrative operational support functions taken over from client agencies more effective, and to find ... explanations for the results so far achieved by the Service Centre. The audit has also aspired to illustrate how agencies that do not subscribe to the services regard their potential for doing so ... . These viewpoints have been analysed with a special focus on the conditions that applied to the Service Centre when it was formed and the measures taken by the Government and the Service Centre in the first years. ... ... Has Swedish public administration become more effective? ... in achieving economies of scale. In addition, the Government has instructed agencies to review the question of subscription and report their reasons for delaying subscription. ... The Service Centre – payroll and financial administration IT system for Swedish public agencies under the government – has achieved the target of a subscription rate of 25 per cent of the total ... number of state employees. However, subscription to the Service Centre was initially slower than the Government had predicted and meant lower revenues than expected in autumn 2013. The Service Centre
Full description
Swedish National Audit Office , issued in 2016
Risk cases: 2
Central government staff costs
Results of staff reductions The British NAO found that departments had significantly reduced numbers of their civil servants and of course salary costs at the same time. But they reduced staff numbers mainly by minimising recruitment, and the age profile of the civil service has changed. NAO pays a lot attention to what effect this has had on the future pipeline of talent and skills. It reminds also that the departments need long-term operating models to work efficiently with the staff reduced.
Full description
National Audit Office , issued in 2015
Risk cases: 5
The effectiveness of Official Development Assistance expenditure
Need of more coordination and transparency The audit of the UK's Official Development Assistance revealed among others: fragmented responsibilities and difficulties in review and reporting. These led to difficulties in assessment of effectiveness of the assistance and of progress in implementing the UK Aid Strategy.
Full description
National Audit Office , issued in 2019
Risk cases: 4
Building and Implementing the Phoenix Pay System
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Office of theAuditor Generalof Canada , issued in 2018
Risk cases: 3
Software Developement Effective Practices and Federal Chalenges in Applying Agile Methods
To identify effective practices in applying Agile for software developement solutions and federal challenges in implementing Agile techniques. ... Agile project approach in government practice ... Useful products delivered in a short time are basis for often applauded features of agile project approach. Applied by many private companies, it tends as well to be more and more popular among state ... administrations. American GAO reviewed set of agile projects and revealed - apart from advantages - a set of commonly occurring problems: poor team work, lack of time and deficit of customers’ trust.
Full description
General Accountability Office , issued in 2012
Risk cases: 4
Digital transformation in government
Support exemplars, provide consistent guidance... and do not lose focus As the NAO states: Government faces significant challenges in providing public services. While many government services are now available online, public administration is struggling to manage more complicated programmes and to improve the complex systems and processes that support public services.
Full description
National Audit Office , issued in 2017
Risk cases: 4
Use of consultants and temporary staff
New skills needed in a longer term UK NAO: Used well, consultants and temporary staff can be an important source of specialist skills and capabilities that are uneconomic for departments to maintain in their permanent staff. Since 2009-10, the government has used spending controls to reduce its use of consultants and temporary staff, and by 2014-15 spending had fallen by £1.5 billion. However, spending has increased by between £400 million and £600 million since 2011-12, suggesting that this was more of a short-term reduction than a sustainable strategy. In the longer term, departments will need to develop workforce, skills and capacity plans to reduce their dependence on external skills. They will need to improve their strategic workforce planning to determine where they can deploy existing staff, where they need to recruit, and where they need to engage temporary resources. Without this, departments cannot demonstrate that they are achieving value for money from the use of consultants and temporary staff.
Full description
National Audit Office , issued in 2016
Risk cases: 7
Identifying and meeting central government's skills requirements
Start with well managed responsibilities UK Departments have invested heavily in skills development. Government estimates that expenditure on formal training, including salary costs of departmental learning and development staff, was £275 million in 2009-10. NAO identified weaknesses of the system which start with devolved responsibilities, lead to: weak data, mis-profiled trainings, doubtful personal decisions, lack of well-targeted evaluation - and finish at more expensive buying-in and retaining key skills...
Full description
National Audit Office , issued in 2011
Risk cases: 6
23 results found. Page 1 of 3 next