Building and Implementing the Phoenix Pay System
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Office of theAuditor Generalof Canada , issued in 2018
Risk cases: 3
OMB and Agencies Need to Focus Continued Attention on Implementing Reform Law
How to invest efficiently in IT IT investments are large and growing position in annual budgets. Historically, they have frequently failed, incurred cost overruns and schedule slippages, or contributed little to mission-related outcomes. GAO recommendations focus on the oversight and execution of the data center consolidation initiative, the accuracy and reliability of the IT Dashboard, and incremental development policies.
Full description
General Accountability Office , issued in 2016
Risk cases: 3
IT Police Systems
Implementation by the Polish Police of two IT projects (E-police station and Command Support System - CSS) was audited. Both systems were to relieve the Police officers and increase the quality ... and effectiveness of their work. Audit explained the reason of failure in the case of E-police station project and success in the case of CSS. Although some irregularities occurred in both cases, careful planning ... and organization of the project turned out to make the difference. Accordance with the public procurement law was not part of the audit as a separate investigation in that matter was carried by respective Polish ... ... A textbook example of how not to implement the IT projects ... Polish NIK compared the implementation of two flagship IT projects of the Police HQ: successful 'Command Support System' and problematic 'E-police station'. List of interesting problems appeared...
Full description
Supreme Audit Office of Poland , issued in 2013
Risk cases: 5
The effectiveness of Official Development Assistance expenditure
Need of more coordination and transparency The audit of the UK's Official Development Assistance revealed among others: fragmented responsibilities and difficulties in review and reporting. These led to difficulties in assessment of effectiveness of the assistance and of progress in implementing the UK Aid Strategy.
Full description
National Audit Office , issued in 2019
Risk cases: 4
Is the project 'E-health in Latvia' a step towards the right direction?
Objective of the audit was to verify efficiency and productivity of the actions by the institutions in charge for implementation of the e-health, as well as to audit economy and productivity of use ... of funds invested in the project for achievement of set objectives and gaining the planned benefits. Audit covered such main questions: 1) Will the e-health policy be able to solve problems and achieve ... the objective? 2) Are the actual activities performed by the National Health Service justified for achievement of the set objectives? 3) Will necessary information security and personal data protection be ensured ... E-health is a step forward in right direction, but not all objectives will be reached! ... a step towards the right direction then. However, as found the Latvian SAI, the e-health policy will not be implemented within the initially planned scope and deadline and within set data security levels ... Project “E-health in Latvia” supports healthy lifestyle, it will provide valuable and accessible information and will promote more efficient provision of services to patients. It is undoubtedly ... , thus the objective of this policy – to promote more effective provision of healthcare services will be attained only partially.
Full description
State Audit Office of the Republic of Latvia , issued in 2015
Risk cases: 3
Effectiveness of the Tax Administration of the Republic of Slovenia in the execution of modernisation projects of the Slovenian duty information system and decreasing the number of duty sub-accounts
of the European Union budget. In order to improve its operations, the Tax Authority decided to modernise the Slovenian duties’ collection information system. It used this opportunity to implement also a second ... some improvements and had also enabled implementation of the second project - decreasing the number of government duty sub-accounts. Despite these successes, the combined projects of modernisation ... The Tax Administration of the Republic of Slovenia (hereinafter: the Tax Administration) is responsible for collecting taxes, fees and other compulsory levies (hereinafter: duties ... ... Shaky coordination of investments in important systems ... Slovenian SAI traced a series of problems in management of crucial IT investments in tax administration. Apart from promising goals, unclear business case gave a start to many problems at next stages ... of the project, involving additional spendings, delays and errors in data processing.
Full description
Court of Audit of the Republic of Slovenia , issued in 2014
Risk cases: 7
Australian Taxation Office: Administration of Australian Business Number Registrations
More elligibility and data integrity needed The Australian Business Number (ABN) and Australian Business Register initiatives were implemented as part of theGovernment's comprehensive reform of the taxation system in 2000. Their introduction involved challenging issues of technology and governance , including the imperative to process and register significant numbers of applications in a short time. Overall, the Australian SAI concluded that the ABN registration process is operating effectively. However, matters relating to the eligibility of some ABN applicants need to be reviewed. Further, some data integrity issues remain outstanding.
Full description
The Australian National Audit Office , issued in 2003
Risk cases: 3
FEMA Needs to Address Management Weaknesses to Improve Its Systems
Controls in emergency management GAO audited the agency of the Department of Homeland Security, responsible for federal efforts to mitigate, respond to, and recover from disasters. American auditors recommend that the agency fully define its investment board’s roles and responsibilities and procedures for selecting and overseeing investments, update its strategic plan and complete plans for IT modernization, and establish time frames for completing workforce planning efforts. The agency should also establish policies and guidance for implementing key IT management controls.
Full description
General Accountability Office , issued in 2016
Risk cases: 4
Relocation of government jobs
Difficult experience of relocation of jobs The Danish government decided to move almost 4 thousand government jobs away from the metropolitan area. The purpose of the relocation was to attain a better balance and development across Denmark and ensure that government institutions were located close to the citizens and businesses. Study of the SAI Denmark shows that overall, the departments have implemented the whole operation in an appropriate manner. At the same time, however, the relocation had negative consequences for the institutions’ production which has also affected citizens and businesses.
Full description
National Audit Office of Denmark , issued in 2017
Risk cases: 4
Audit to the Social Security Systems of Collection of Contributions and Quotes and Relationship with Banking and other Entities Engaged in Collection Initiatives
The audit aims to evaluate the effectiveness and efficiency of the processes implemented in respect of the processing schemes of contributions/quotas, whose Wages Statements (WS) entered ... into the system in the first quarter of 2007, test the reliability, stability and confidence level of the application systems developed and the respective values processed in the entire collection circuit ... and respective accounting, and also check compliance with the contracts celebrated with banking entities. ... ... Application level of Social Security IS analyzed ... Processes maturity and automation of controls appeared to be main problems in the system which reliability, stability and confidence level were tested.
Full description
TRIBUNAL DE CONTAS DE PORTUGAL , issued in 2008
Risk cases: 2