Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
2 results found in 4 ms Page 1 of 1
Municipalities’ internal control system – Audit of the establishment and operation of the internal control system of municipalities – on the audit of Rudabánya
Incomplete internal control The SAI Hungary published the compliance audit of the establishment and operation of the internal control system, as well as certain investment decisions, their implementation and accounting at the Local Government of Rudabánya. Apart from positive findings, some accounting irregularities and insufficient controls established to ensure organisational integrity were pointed out.
Full description
State Audit Office of Hungary , issued in 2018
Risk cases: 2
Building and Implementing the Phoenix Pay System
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Office of theAuditor Generalof Canada , issued in 2018
Risk cases: 3
2 results found. Page 1 of 1