Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
15 results found in 11 ms Page 1 of 2
Supply of food and medicinal products
Supply of food and medicinal products Deficiencies in emergency preparedness and weaknesses in governance are still found by the Swedish NAO in the system of safeguarding supply of food and medicinal products. The system is complex and NAO appreciates efforts made by responsible agencies. However, they found also insufficient clarity in division of responsibilities and weaknesses in coordinantion.
Full description
Swedish National Audit Office , issued in 2018
Risk cases: 2
Extract from the report to the Public Accounts Committee on the access to IT systems that support the provision of essential services to the Danish society
The report is focused on the significant risk that is associated with inadequate management and control of domain administrator privileges, which makes it possible for unauthorized persons to obtain ... access to the IT systems and data of the institutions. Rigsrevisionen has not examined for what specific purposes unauthorized access to the institutions’ systems and data can be used. ... ... Inadequate management and control of domain administrator privileges ... services to the Danish society from unauthorized access, obtained on the basis of domain administrator privileges. ... The Danish report concerns the measures - taken by six government institutions of various branches of State activities - to protect IT systems and data that support the provision of essential
Full description
National Audit Office of Denmark , issued in 2015
Risk cases: 4
Federal Agencies Need to Address Aging Legacy Systems
Be aware of legacy IT risks The US government spends about 75 percent of the total amount budgeted for information technology on operations and maintenance. GAO reviewed Office of Management and Budget and 26 agencies, covering years 2010 through 2017 and recommends to develop a goal for spending measure and finalize guidance to identify and prioritize legacy IT needing to be modernized or replaced.
Full description
General Accountability Office , issued in 2016
Risk cases: 3
Information security work at nine agencies
Difficulties in achieving appropriate IT security Together with the Swedish NAO we assume that the picture that emerges at the agencies audited applies also to most of the other agencies in the public administration. The information security work is not given high enough priority in relation to the risks that exist. This applies to both the Government, which should have been clearer in its directions to agencies on this matter, and to agency managements, which did not give priority to the work of information security to the extent required. Much indicates that it is difficult for many agencies to achieve an appropriate level of information security work.
Full description
Swedish National Audit Office , issued in 2016
Risk cases: 4
Staff scheduling in government institutions
Scheduling irregular hours work Danish Rigsrevisionen shows in their study problems with staff scheduling in government institutions where employees are required to work irregular hours. Optimized staff scheduling contributed to reducing payroll costs. On the other hand, problems with rearrangement of work, recording working hours, optimisation of staffing levels and analysis of overtime triggers - add up to high costs of workforce. IT is not always used as ally either.
Full description
National Audit Office of Denmark , issued in 2015
Risk cases: 5
The National Offender Management Information System (NOMIS)
for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... with offenders (end-to-end services). ... This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... Rescoping necessary, but not fully successful ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits.
Full description
National Audit Office , issued in 2009
Risk cases: 4
Data security and positions with access to confidential information
. The 2007 Civil Service Data Information Security Decree (in Dutch: VIR 2007) is the legal foundation of the first part of this audit (data security). The Security Screening Act (in Dutch: WVO ... ) is the foundation of the second part (positions with access to confidential information). Only four of the organizations we have audited show an acceptible level of compliance with the 2007 Civil Service Data ... Information Security Decree, eight organizations show scope for improvement and nine organizations show an unsatisfactory level of compliance with the 2007 Civil Service Data Information Security Decree. When ... ... Shortcomings in information security and in positions with access to confidential information ... Surprising weaknesses were revealed by the NCA in its Government-wide operational audit performed as part of the 2011 audit into the state of central government accounts: Poor quality of data ... protection policy and poor protection of information systems. Also, non vetted positions with access to confidential information.
Full description
Netherlands Court of Audits , issued in 2012
Risk cases: 3
Material–technical supply of the State Police
The main aim of the audit was to obtain assurance about whether the State budget funds allocated for material–technical supply of functions of the State Police were legitimate and efficient ... . The audit included inspections performed at the State Police, the Ministry of the Interior and the Information Centre and focused on: the Biometric data processing system and the Criminal Procedure ... information system. ... ... Essential role of pre-project evaluation ... SAI of Latvia reveals chain of events that lead to unsuccessful implemenation of two important IS of the State police. What started with an absence of the strategy ended up with budget, time ... overruns and an IS not ready for effiecient use.
Full description
State Audit Office of the Republic of Latvia , issued in 2013
Risk cases: 6
IT Support in the Judicial Chain
The Swedish National Audit Office has examined how well agencies in the judicial chain have handled known flaws in their IT support and whether the Government’s control mechanisms have provided ... the agencies with sufficient prerequisites to expand and improve IT support. ... ... Needed: good conditions by government, better steering and control by authorities ... Despite many years’ of work to modernize the IT support within the judiciary, there are still many deficiencies. The Government has not given the authorities good conditions enough to lead the work ... . The authorities, in their turn, need to improve their steering and control, as well as interact to a much higher degree.
Full description
Swedish National Audit Office , issued in 2011
Risk cases: 3
Performance Audit of the Management of ICT in the Criminal Justice Sector
The Norwegian OAG has assesed how the Ministry of Justice and Public Security has discharged its responsibility for effiecient case processing through developing and applying Information ... and Communications Technology (ICT) in the criminal justice sector ... ... Unclear signals from a Ministry weaken development of ICT in the justice chain ... Points by SAI Norway: development of an overall rolling action plan based on the current ICT (Information and Communication Technology) strategy for the justice sector, performance-oriented ... reporting from the subordinate agencies, ensuring that the new ICT Police System takes into account other sub-sectors need for electronic interaction.
Full description
Office of the Auditor General of Norway , issued in 2012
Risk cases: 2
15 results found. Page 1 of 2 next