Lessons learned from government ICT-projects
This audit has been performed on request of the Dutch parliament. Some newspapers mentioned government losses of four to five billion euro's on a yearly bases. These news items caused the parliament ... to request this audit. The audit has been performed in only 5 months time and consisted of the re-use of earlier performed audits. We have 'recycled' earlier findings about ICT-projects. ... 'Expensive' does not always mean 'High Quality', so... do not feed the spiral ... Excellent analysis of systemic errors commited when designing Government IT projects. The report aims at the essence of problems which are encountered far from information technologies - in: politics ... , business, psychology... Do not be mislead by date of report, it is evergreen for all who really want to know why IT projects fail.
Full description
Netherlands Court of Audits , issued in 2007
Risk cases: 3
Managing the risk of legacy ICT to public service delivery
The cross-government report describes the case studies from four public services (state pension, Value Added Tax collection, prescription payment and consumer credit licensing services) selected ... to illustrate the range of approaches that small and large government bodies are taking to address the issues arising from legacy ICT (defined as "systems and applications that have been operationally embedded ... within a business function but superseded by newer and more effective technologies or changed business needs"). ... Possible approaches to the problem of 'legacy ICT' ... UK’s government experience in managing the risks connected to legacy ICT provides valuable insight for others facing the same problem and are considering transforming their services.
Full description
National Audit Office , issued in 2013
Risk cases: 3
Public access point to the Polish e-Administration
and public report issued in March 2009. Primary goal of th presentation was intended to illustrate the use of 'e-Government Algorithm' elaborated by EUROSAI IT Working Group in 2005. One of issues mede better ... Coordinated audit series (46 auditees) focused on a web solution applied to give an easy access to Government e-services (the project planned to be completed in 2013) The audit was performed in 2008 ... known by the audit was 'Project Frameworks vs Public Procurement'. ... ... Buyer, provider and methodologies need a balance ... Presentation based on a vast audit by Polish SAI which subject was of big network project aiming to provide one access point to Government and Selfgovernments services. The presentation illustrates ... old EUROSAI IT Wg 'Algorithm approach' and focuses on procurement systemic problems.
Full description
Supreme Audit Office of Poland , issued in 2008
Risk cases: 3
The National Offender Management Information System (NOMIS)
This report examines the reasons for the delays and cost increases to the original integrated information system and, since the moratorium imposed by the Minister of State in order to seek options ... for project’s cost reduction, the aims of the revised National Offender Management Service (NOMS) and the progress made, the impact of the delays and rescoping on the costs and benefits achieved, and NOMS ... ’ fitness to deliver. The aim of one integrated information system (C-NOMIS i.e. National Offender Management Information System) was to improve information sharing about offenders; address the lack ... Rescoping necessary, but not fully successful ... An initiative to build a single offender management IT system for the prison and probation services has not delivered value for money. The NAO investigation found the project had been hampered ... by poor management leading to a three-year delay, a doubling in project costs and reductions in scope and benefits.
Full description
National Audit Office , issued in 2009
Risk cases: 4
Performance Audit of the Georgian Government electronic Procurement system
State procurement is one of the key components of public financial management. Its share in state budget is approximately 25 percent. Effective management of state procurements is an important sphere ... of interest for the State Audit Office. Considering the fact that since 2010 major part of public procurements is being conducted electronically and there is no alternative tool, uninterrupted provision ... of a high-quality service has a particular importance. <br /> It is noteworthy that establishment of open, transparent and competitive environment for the procurement parties mitigates the risks of corruption ... ... Electronic procurement system - how effective are management and control mechanisms? ... SAI Georgia analyzed the electronic Government Procurement system. In their report they focus on compliance and security problems, which may harm the business goals and overall mission of the system.
Full description
State Audit Office Of Georgia , issued in 2016
Risk cases: 5
Risks of e-Governance Strategy Dominated by Outsourcing
Audit of IT service in Ministry of Public Assets gave an opportunity to analize risks related to outsourcing dominated e-Governance strategy. Important findings were identified in preparation ... and testing stages, stemming from poor Business Case. ... ... IT outsourcing risks ... Presentation based on audit of IT services in Polish Ministry of Public Assets. Outsourcing risks were classified and next identified at Business Case, preparation and teststing stages.
Full description
Supreme Audit Office of Poland , issued in 2010
Risk cases: 4