Reports Search Reports Spatial Search Risk-cases Search Risk-cases Graph Traversal
26 results found in 9 ms Page 1 of 3
Building and Implementing the Phoenix Pay System
Expensive IT project became a failure Phoenix project (development of states pay system) was an incomprehensible failure of project management and oversight. Phoenix executives prioritized certain aspects, such as schedule and budget, over other critical ones, such as functionality and security. Phoenix executives did not understand the importance of warnings that the Miramichi Pay Centre, departments and agencies, and the new system were not ready. They did not provide complete and accurate information to deputy ministers and associate deputy ministers of departments and agencies, including the Deputy Minister of Public Services and Procurement, when briefing them on Phoenix readiness for implementation.
Full description
Office of theAuditor Generalof Canada , issued in 2018
Risk cases: 3
Federal Agencies Need to Address Aging Legacy Systems
Be aware of legacy IT risks The US government spends about 75 percent of the total amount budgeted for information technology on operations and maintenance. GAO reviewed Office of Management and Budget and 26 agencies, covering years 2010 through 2017 and recommends to develop a goal for spending measure and finalize guidance to identify and prioritize legacy IT needing to be modernized or replaced.
Full description
General Accountability Office , issued in 2016
Risk cases: 3
FEMA Needs to Address Management Weaknesses to Improve Its Systems
Controls in emergency management GAO audited the agency of the Department of Homeland Security, responsible for federal efforts to mitigate, respond to, and recover from disasters. American auditors recommend that the agency fully define its investment board’s roles and responsibilities and procedures for selecting and overseeing investments, update its strategic plan and complete plans for IT modernization, and establish time frames for completing workforce planning efforts. The agency should also establish policies and guidance for implementing key IT management controls.
Full description
General Accountability Office , issued in 2016
Risk cases: 4
Products sold on the European market: unravelling the system of CE marking
Problems with general picture The Netherlands National Court of Audit was interested in finding out whether anyone keeps track of all the actors involved in the process of system of European Union product markings. The interest was aroused by an observation that the vast majority of the questions raised about the system were prompted by incidents and that the questioners did not generally appear to be interested in the operation of the system as a whole...
Full description
The Netherlands Court of Audit , issued in 2017
Risk cases: 5
Performance measurement by regulators
Performance measurement for regulators Primary adressees of this good practice guide - by the British NAO - are regulators, the public institutions established for making sure that an industry or system works legally and fairly. But we are sure that many more can find this guidance useful - including auditors. NAO presents a comprehensible framework for performance measurement and hints how to focus on influence that regulators can use.
Full description
National Audit Office , issued in 2016
Risk cases: 2
Digital transformation in government
Support exemplars, provide consistent guidance... and do not lose focus As the NAO states: Government faces significant challenges in providing public services. While many government services are now available online, public administration is struggling to manage more complicated programmes and to improve the complex systems and processes that support public services.
Full description
National Audit Office , issued in 2017
Risk cases: 4
Conflicts of interest
First, recognise the conflicts of interest are a real risk the British NAO gathered a significant amount of intelligence on conflicts, particularly in the health and education sectors. These are areas of government where services are increasingly commissioned and delivered by parties at arm’s-length to departments. Conflicts of interest can occur naturally as a product of the way a system is designed and most often arise from operational situations.
Full description
National Audit Office , issued in 2015
Risk cases: 8
The effectiveness of Official Development Assistance expenditure
Need of more coordination and transparency The audit of the UK's Official Development Assistance revealed among others: fragmented responsibilities and difficulties in review and reporting. These led to difficulties in assessment of effectiveness of the assistance and of progress in implementing the UK Aid Strategy.
Full description
National Audit Office , issued in 2019
Risk cases: 4
WannaCry Cyber Attack and the NHS
Why the British NHS became a victim of WannaCry The NAO's investigation points at the problem of insufficient powers of the cybersecurity coordinator across the health organisation. As a result no remedial actions were taken, and the cyber attack succeeded thanks to neglected precautions.
Full description
National Audit Office , issued in 2017
Risk cases: 3
Improved Planning and Performance Measures Are Needed to Help Ensure Successful Technology Modernization
Massive modernization effort needs coordination Social security issues can touch lives of many. Information technology in this area are increasingly costly and difficult to maintain. GAO is recommending to develop comprehensive metrics to effectively gauge modernization progress; complete comprehensive strategic planning, including its enterprise architecture; and define the new roles and responsibilities to help ensure effective oversight.
Full description
General Accountability Office , issued in 2012
Risk cases: 3
26 results found. Page 1 of 3 next